Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Dadra and Nagar Haveli and Daman and Diu. Most of our published work is megawatt-scale rooftop plants on working industrial sites.
Metering rules for business rooftops in Dadra and Nagar Haveli and Daman and Diu
In Dadra and Nagar Haveli and Daman and Diu, a consumer can connect a rooftop, ground-mounted or floating solar plant of up to 500 kWp at one premises under JERC's net metering regulations of 2019, as amended in 2024. A plant above 500 kWp comes under net billing (net feed-in). The plant may not be larger than the consumer's contract demand or sanctioned load. The plant may be owned by the consumer or by a third party.
- Under net billing, power drawn from the grid is charged at the retail tariff and solar power sent to the grid is valued at the feed-in tariff set by the Commission.
- Gross metering is allowed for a consumer or generator who chooses to sell all the solar power to the distribution licensee at the feed-in tariff set by the Commission.
- The total solar capacity connected to one distribution transformer may not exceed 75% of that transformer's capacity. The licensee may allow more after a detailed load study.
- Under net metering, surplus units carry forward to the next billing period. Units still unadjusted at the end of the financial year are bought by the licensee at its average power purchase cost or the feed-in tariff, whichever is lower.
- Group net metering is open to all consumers. Virtual net metering is for residential consumers, group housing societies and establishments of government or local authorities. Under both, the plant may be up to 500 kWp or the sanctioned load, whichever is lower.
- A consumer may lease the roof or land to a solar developer under net metering. Plants under these regulations are exempt from open access charges and from banking charges.
- The licensee must finish the technical feasibility study within 15 working days. An application for a plant up to 10 kW is deemed accepted without the study.
- Latest amendment: the First Amendment Regulations, 2024, notified on 1 August 2024 and published in the Gazette of India on 11 September 2024.
Output and bill value for a rooftop plant in Dadra and Nagar Haveli and Daman and Diu
Solar output changes across Dadra and Nagar Haveli and Daman and Diu with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,370 to 1,500 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Daman | 1,380 | 1,430 |
| Diu | 1,500 | 1,540 |
| Silvassa | 1,370 | 1,410 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
How a factory or commercial rooftop project runs
Rooftop plants on working buildings are planned around the roof, the load and the production schedule.
- Roof check: sheet or concrete, load capacity, shading and safe access
- Sizing against daytime load and sanctioned demand, within the metering rules above
- Mounting design to suit the roof, including corrosion protection where the air is harsh
- Installation in stages so production carries on
- Testing, metering and connection with the electricity supplier
- Monitoring and maintenance after handover, where contracted
More detail: Commercial & Industrial Solar across India.
Questions about solar projects in Dadra and Nagar Haveli and Daman and Diu
Is net metering available for factories and commercial buildings in Dadra and Nagar Haveli and Daman and Diu?
In Dadra and Nagar Haveli and Daman and Diu, a consumer can connect a rooftop, ground-mounted or floating solar plant of up to 500 kWp at one premises under JERC's net metering regulations of 2019, as amended in 2024. A plant above 500 kWp comes under net billing (net feed-in). The plant may not be larger than the consumer's contract demand or sanctioned load. The plant may be owned by the consumer or by a third party.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Dadra and Nagar Haveli and Daman and Diu
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- JERC (Solar PV Grid Interactive System based on Net Metering) Regulations, 2019 (No. JERC-24/2019, notified 24 July 2019) and the Net Metering & Gross Metering (First Amendment) Regulations, 2024 (notified 1 August 2024, Gazette of India 11 September 2024)
- PVGIS, European Commission Joint Research Centre (solar output model)