Somaya Solar Solutions Limited is a solar EPC company based in Ghaziabad, Uttar Pradesh. We design, supply, install and commission solar plants for factories, commercial buildings, institutions, landowners and PM-KUSUM developers in Obra, Uttar Pradesh.
Obra at a glance for solar projects
| District and state | Sonbhadra district, Uttar Pradesh |
|---|---|
| Electricity supply | Purvanchal Vidyut Vitran Nigam Limited (PuVVNL) supplies electricity in Sonbhadra district, one of the districts it lists as its area. |
| Electricity regulator | Uttar Pradesh Electricity Regulatory Commission (UPERC) |
| State renewable energy agency | Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) |
| State solar policy | Uttar Pradesh Solar Energy Policy 2022 (five-year term, unless replaced earlier) |
| Rooftop metering for businesses | Net billing or gross metering; no net metering for industry or commerce |
| Modelled solar output | about 1,380 units (kWh) a year for each kW installed |
| Somaya Solar office | Ghaziabad, Uttar Pradesh, about 720 km from Obra in a straight line |
Solar services in Obra
- Solar EPC Company in Obra
Design, supply, installation and commissioning of rooftop and ground-mounted plants under one contract. - Commercial & Industrial Solar in Obra
Rooftop solar for factories, warehouses, institutions and commercial buildings. - Ground-Mounted Solar Plant in Obra
Solar plants on open land for captive use or sale of power. - Utility-Scale Solar in Obra
Megawatt-scale plants that feed the grid or supply large consumers. - PM-KUSUM in Obra
EPC for farmer-owned and feeder-level solar plants under the PM-KUSUM scheme. - Turnkey Solar EPC in Obra
One contract from survey to a working plant, with approvals and handover included.
Solar output in Obra
A solar plant in Obra is modelled to produce about 1,380 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the Large and Heavy Power (HV-2, supply up to 11 kV, urban schedule) energy charge of ₹7.10 per kVAh (UPERC tariff order of 2 July 2026 for 2026-27). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. This charge is billed per kVAh. The table counts one kWh as one kVAh, which is close when the power factor is near 1.
| Plant size | Modelled output a year | Shadow-free roof needed (typical) | Value at ₹7.10 per kVAh |
|---|---|---|---|
| 100 kW | 1.4 lakh units | 1,000 sq m | ₹9.8 lakh |
| 500 kW | 6.9 lakh units | 5,000 sq m | ₹49.0 lakh |
| 1 MW | 13.8 lakh units | 10,000 sq m | ₹98.0 lakh |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
Solar output by month in Obra
For a rooftop array in Obra the strongest month is April, at about 142 units for each kW installed, and the weakest is July, at about 90. For a ground-mounted array at a 29° tilt the strongest month is March (about 147) and the weakest is July (about 82). A plant that serves a steady load is best checked against the weakest months.
| Month | Rooftop, 10° tilt (kWh per kW) | Ground-mounted, best fixed tilt (kWh per kW) |
|---|---|---|
| January | 114 | 138 |
| February | 119 | 135 |
| March | 141 | 147 |
| April | 142 | 137 |
| May | 140 | 128 |
| June | 111 | 99 |
| July | 90 | 82 |
| August | 90 | 85 |
| September | 98 | 99 |
| October | 115 | 126 |
| November | 110 | 130 |
| December | 110 | 135 |
Somaya Solar projects near Obra
These are the Somaya Solar projects closest to Obra, with straight-line distances. They are shown as references and are not in Obra unless the line says so.
- KUSUM-C, Ram Sati Devi: 2.4 MW ground-mounted plant under PM-KUSUM Component C, Katni, Madhya Pradesh, about 270 km from Obra. Completed, including the transmission line work coordinated with the local distribution company.
- KRIBHCO: 2 MW rooftop plant, Shahjahanpur, Uttar Pradesh, about 490 km from Obra. Fertiliser plant; the structures carry a special coating against corrosion. Five years of operation and maintenance.
- Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 670 km from Obra. Completed in two months, with five years of operation and maintenance.
Questions about solar projects in Obra
Which electricity company handles solar connections in Obra?
Purvanchal Vidyut Vitran Nigam Limited (PuVVNL) supplies electricity in Sonbhadra district, one of the districts it lists as its area.
Is net metering available for factories and commercial buildings in Obra?
Net billing or gross metering; no net metering for industry or commerce. The rule is the same across Uttar Pradesh.
How much electricity does a solar plant generate in Obra?
About 1,380 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 13.8 lakh units a year. A site study gives the figure to plan on.
Where is Somaya Solar based, and how far is that from Obra?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 720 km from Obra in a straight line. The closest published project is KUSUM-C, Ram Sati Devi (2.4 MW ground-mounted plant under PM-KUSUM Component C) in Katni, about 270 km away.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Obra
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- GeoNames (place coordinates, CC BY 4.0)
- PVGIS, European Commission Joint Research Centre (solar output model)
- PuVVNL official website, Profile page
- UPERC (Rooftop Solar PV Grid Interactive Systems Gross/Net Metering) Regulations, 2019, with amendments of 1 June 2022, 17 November 2023 and 3 June 2025; UPERC tariff order of 2 July 2026, paragraph 3.13.5
- UPERC tariff order for 2026-27 for the state distribution companies, dated 2 July 2026
- Uttar Pradesh Electricity Regulatory Commission
- Uttar Pradesh Solar Energy Policy 2022 (Government of Uttar Pradesh)
- e-Nagarsewa Uttar Pradesh portal (e-nagarsewaup.gov.in), ULB list: Nagar Panchayat