Somaya Solar Solutions Limited takes up megawatt-scale, grid-connected solar plants in Pathankot, Punjab as an EPC contractor: engineering, supply, construction and commissioning.
What Punjab's policy says about large solar plants
Punjab's renewable energy policy is the New and Renewable Sources of Energy (NRSE) Policy, 2012. It was notified on 26 December 2012 and amended on 9 July 2015. It stays in operation until the government notifies a new policy, and a draft state policy published in 2026 still relies on it.
Punjab has no separate green energy open access regulation. The rules sit in the PSERC Intra-State Open Access Regulations, 2011, last changed by the 13th amendment of 12 May 2026. A consumer with a sanctioned contract demand of 100 kVA or more can take renewable power through open access. Connections in the same electricity division can be added together to reach 100 kVA.
The charges, exemptions and conditions for Punjab are on the page Utility-Scale Solar in Punjab.
Output and land at megawatt scale in Pathankot
A solar plant in Pathankot is modelled to produce about 1,420 units (kWh) a year for each kW installed, for a ground-mounted array at the best fixed tilt (35°).
| Plant size | Modelled output a year | Land needed (typical) |
|---|---|---|
| 5 MW | 71.0 lakh units | 20 to 25 acres |
| 10 MW | 1.42 crore units | 40 to 50 acres |
| 25 MW | 3.55 crore units | 100 to 125 acres |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
What utility-scale work involves
At megawatt scale the grid connection, land and delivery schedule decide the project as much as the equipment does.
- Land and grid-connection feasibility
- Detailed engineering for the plant and the evacuation system
- Procurement and logistics for modules, inverters, transformers and structures
- Civil, mechanical and electrical construction with several teams working in parallel
- Testing, commissioning and connection with the transmission or distribution utility
- Operation and maintenance, where contracted
More detail: Utility-Scale Solar across India.
Megawatt-scale ground-mounted work by Somaya Solar near Pathankot
These are the Somaya Solar projects closest to Pathankot, with straight-line distances. They are shown as references and are not in Pathankot unless the line says so.
- KUSUM-A, Bhavnath Singh: 2.4 MW ground-mounted plant under PM-KUSUM Component A, Amroha, Uttar Pradesh, about 460 km from Pathankot. In progress. Site access was difficult and was handled with local support.
- KUSUM-C, Ram Sati Devi: 2.4 MW ground-mounted plant under PM-KUSUM Component C, Katni, Madhya Pradesh, about 1050 km from Pathankot. Completed, including the transmission line work coordinated with the local distribution company.
Questions about solar projects in Pathankot
Which electricity company handles solar connections in Pathankot?
Punjab State Power Corporation Limited (PSPCL) is the distribution utility for Punjab and supplies Pathankot district.
How much electricity does a solar plant generate in Pathankot?
About 1,420 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 14.2 lakh units a year. A site study gives the figure to plan on.
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based, and how far is that from Pathankot?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 440 km from Pathankot in a straight line. The closest published project is KUSUM-A, Bhavnath Singh (2.4 MW ground-mounted plant under PM-KUSUM Component A) in Amroha, about 460 km away.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Pathankot
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- GeoNames (place coordinates, CC BY 4.0)
- New and Renewable Sources of Energy (NRSE) Policy, 2012, Government of Punjab notification of 26 December 2012, with the amendment of 9 July 2015
- PSERC (Terms and Conditions for Intra-State Open Access) Regulations, 2011, 10th Amendment of 2 June 2023 to 13th Amendment of 12 May 2026; PSERC tariff order for 2026-27 dated 6 March 2026; PSERC additional surcharge orders of 11 June 2026 and 30 September 2026
- PSERC Tariff Order FY 2026-27 for PSPCL (order dated 06 March 2026), Chapter 1, page 1
- PVGIS, European Commission Joint Research Centre (solar output model)