Somaya Solar Solutions Limited takes up megawatt-scale, grid-connected solar plants in Shimla, Himachal Pradesh as an EPC contractor: engineering, supply, construction and commissioning.
What Himachal Pradesh's policy says about large solar plants
The Swaran Jayanti Energy Policy, 2021 is the state's energy policy. The Government of Himachal Pradesh notified it on 20 January 2022 and has amended it since. The regulator applied it in orders of 22 July 2026 and 9 October 2026.
HPERC's tariff order for 2026-27 says open access is permitted for all consumers with a contracted demand or connected load above 100 kW. The order sets the open access charges that apply from 1 April 2026.
The charges, exemptions and conditions for Himachal Pradesh are on the page Utility-Scale Solar in Himachal Pradesh.
Output and land at megawatt scale in Shimla
A solar plant in Shimla is modelled to produce about 1,440 units (kWh) a year for each kW installed, for a ground-mounted array at the best fixed tilt (33°).
| Plant size | Modelled output a year | Land needed (typical) |
|---|---|---|
| 5 MW | 72.0 lakh units | 20 to 25 acres |
| 10 MW | 1.44 crore units | 40 to 50 acres |
| 25 MW | 3.60 crore units | 100 to 125 acres |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
What utility-scale work involves
At megawatt scale the grid connection, land and delivery schedule decide the project as much as the equipment does.
- Land and grid-connection feasibility
- Detailed engineering for the plant and the evacuation system
- Procurement and logistics for modules, inverters, transformers and structures
- Civil, mechanical and electrical construction with several teams working in parallel
- Testing, commissioning and connection with the transmission or distribution utility
- Operation and maintenance, where contracted
More detail: Utility-Scale Solar across India.
Megawatt-scale ground-mounted work by Somaya Solar near Shimla
These are the Somaya Solar projects closest to Shimla, with straight-line distances. They are shown as references and are not in Shimla unless the line says so.
- KUSUM-A, Bhavnath Singh: 2.4 MW ground-mounted plant under PM-KUSUM Component A, Amroha, Uttar Pradesh, about 280 km from Shimla. In progress. Site access was difficult and was handled with local support.
- KUSUM-C, Ram Sati Devi: 2.4 MW ground-mounted plant under PM-KUSUM Component C, Katni, Madhya Pradesh, about 870 km from Shimla. Completed, including the transmission line work coordinated with the local distribution company.
Questions about solar projects in Shimla
Which electricity company handles solar connections in Shimla?
Himachal Pradesh State Electricity Board Limited (HPSEBL) is the distribution utility for Himachal Pradesh and supplies Shimla district.
How much electricity does a solar plant generate in Shimla?
About 1,440 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 14.4 lakh units a year. A site study gives the figure to plan on.
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based, and how far is that from Shimla?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 270 km from Shimla in a straight line. The closest published project is KUSUM-A, Bhavnath Singh (2.4 MW ground-mounted plant under PM-KUSUM Component A) in Amroha, about 280 km away.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Shimla
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- GeoNames (place coordinates, CC BY 4.0)
- HPERC orders of 22 July 2026 (Petition No. 121 of 2026), 9 October 2026 (Petition No. 179 of 2026) and 22 March 2025 (Petition No. 20 of 2025), which apply the Swaran Jayanti Energy Policy, 2021; Directorate of Energy, Government of Himachal Pradesh, scheme for solar power projects above 5 MW (published 10 March 2026)
- HPERC tariff order for HPSEBL for 2026-27, dated 25 March 2026 (chapter 10, Open Access); HPERC (Terms and Conditions for Green Energy Open Access and Banking) Regulations, 2024, notification of 17 December 2024
- HPERC tariff order for HPSEBL, 2026-27 (25 March 2026), para 1.1.4
- PVGIS, European Commission Joint Research Centre (solar output model)