Somaya Solar Solutions Limited builds ground-mounted solar power plants in Basar, Arunachal Pradesh for businesses that want their own power and for landowners and developers who sell power to the grid.

Output and land for a ground-mounted plant in Basar

A solar plant in Basar is modelled to produce about 1,140 units (kWh) a year for each kW installed, for a ground-mounted array at the best fixed tilt (32°).

Plant sizeModelled output a yearLand needed (typical)
1 MW11.4 lakh units4 to 5 acres
2 MW22.8 lakh units8 to 10 acres
5 MW57.0 lakh units20 to 25 acres

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

State policy and open access in Arunachal Pradesh

Under APSERC's Green Energy Open Access Regulations, 2024, a consumer with a contracted demand (HT) or sanctioned load (LT) of 100 kW or more, other than a captive user, can take green power through open access. A captive consumer has no minimum load. The tariff order for 2026-27 sets the wheeling charge.

The charges, exemptions and conditions for Arunachal Pradesh are on the page Ground-Mounted Solar Plant in Arunachal Pradesh.

What a ground-mounted project involves

A ground-mounted plant needs more groundwork than a rooftop one before any module is fixed.

  • Land check: title, slope, soil, drainage, access road and shading
  • Distance to the substation or connection point and the line needed to reach it
  • Layout, structure design and foundations for the soil
  • Supply, installation, testing and commissioning
  • Evacuation line, metering and connection approvals
  • Fencing, cleaning water and maintenance planning

More detail: Ground-Mounted Solar Plant across India.

Ground-mounted projects by Somaya Solar near Basar

These are the Somaya Solar projects closest to Basar, with straight-line distances. They are shown as references and are not in Basar unless the line says so.

  • KUSUM-C, Ram Sati Devi: 2.4 MW ground-mounted plant under PM-KUSUM Component C, Katni, Madhya Pradesh, about 1500 km from Basar. Completed, including the transmission line work coordinated with the local distribution company.
  • KUSUM-A, Bhavnath Singh: 2.4 MW ground-mounted plant under PM-KUSUM Component A, Amroha, Uttar Pradesh, about 1590 km from Basar. In progress. Site access was difficult and was handled with local support.

See all published projects

Questions about solar projects in Basar

Which electricity company handles solar connections in Basar?

Department of Power, Government of Arunachal Pradesh (APDOP) is the distribution utility for Arunachal Pradesh and supplies Lepa Rada district.

How much electricity does a solar plant generate in Basar?

About 1,140 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 11.4 lakh units a year. A site study gives the figure to plan on.

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based, and how far is that from Basar?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 1690 km from Basar in a straight line. The closest published project is KUSUM-C, Ram Sati Devi (2.4 MW ground-mounted plant under PM-KUSUM Component C) in Katni, about 1500 km away.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Basar

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.