Commercial and Industrial Rooftop Solar in Bhopal

Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Bhopal, Madhya Pradesh. Most of our published work is megawatt-scale rooftop plants on working industrial sites.

Local points for solar projects in Bhopal

The Government of India's One District One Product (ODOP) list names Zari Zardozi and Jute Products as the products of Bhopal district.

Metering rules for business rooftops in Bhopal

In Madhya Pradesh, MPERC's Grid Interactive Renewable Energy Systems regulations of 14 March 2024 let consumers of all categories, including commercial and industrial, install rooftop or on-site renewable plants under net metering up to 500 kW. Gross metering is allowed up to 1 MW. Group net metering and virtual net metering are allowed below 100 kW. The regulations were amended on 18 June 2026. There is no net billing option in these regulations.

The size limits, charges and other conditions for Madhya Pradesh are on the page Commercial & Industrial Solar in Madhya Pradesh.

In Bhopal the application for connection and metering goes to MPMKVVCL.

Output and bill value for a rooftop plant in Bhopal

A solar plant in Bhopal is modelled to produce about 1,370 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the HT Industrial (HV-3.1), 11 kV supply energy charge of ₹7.79 per kWh (MPERC retail supply tariff order for FY 2026-27, Petition No. 140/2025, passed 26 March 2026). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. The rate of ₹7.79 per unit applies to energy up to 50% load factor; energy above 50% load factor is ₹6.79. A monthly fixed charge of ₹409 per kVA of billing demand also applies at 11 kV. At 33 kV the energy charge is ₹7.75 and ₹6.70, with a fixed charge of ₹641 per kVA. At 132 kV it is ₹7.34 and ₹6.35, with ₹729 per kVA. At 220/400 kV it is ₹6.89 and ₹5.89, with ₹729 per kVA. Time-of-day rebate or surcharge applies as set in the general terms of the HT tariff. A rebate of ₹1 per unit applies to new HT connections and, as an alternative, to incremental consumption of existing consumers, on the conditions in the order. The rates exclude taxes and duties. The same tariff order covers all three DISCOMs.

Plant sizeModelled output a yearShadow-free roof needed (typical)Value at ₹7.79 per kWh
100 kW1.4 lakh units1,000 sq m₹10.7 lakh
250 kW3.4 lakh units2,500 sq m₹26.7 lakh
500 kW6.8 lakh units5,000 sq m₹53.4 lakh
1 MW13.7 lakh units10,000 sq m₹1.07 crore

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

How a factory or commercial rooftop project runs

Rooftop plants on working buildings are planned around the roof, the load and the production schedule.

  • Roof check: sheet or concrete, load capacity, shading and safe access
  • Sizing against daytime load and sanctioned demand, within the metering rules above
  • Mounting design to suit the roof, including corrosion protection where the air is harsh
  • Installation in stages so production carries on
  • Testing, metering and connection with the electricity supplier
  • Monitoring and maintenance after handover, where contracted

More detail: Commercial & Industrial Solar across India.

Rooftop projects by Somaya Solar near Bhopal

These are the Somaya Solar projects closest to Bhopal, with straight-line distances. They are shown as references and are not in Bhopal unless the line says so.

  • KRIBHCO: 2 MW rooftop plant, Shahjahanpur, Uttar Pradesh, about 570 km from Bhopal. Fertiliser plant; the structures carry a special coating against corrosion. Five years of operation and maintenance.
  • Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 680 km from Bhopal. Completed in two months, with five years of operation and maintenance.
  • Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand, about 750 km from Bhopal. Included net-metering coordination with the local electricity distribution company.

See all published projects

Questions about solar projects in Bhopal

Which electricity company handles solar connections in Bhopal?

Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited (MPMKVVCL) supplies electricity in Bhopal district, one of the districts it lists as its area.

Is net metering available for factories and commercial buildings in Bhopal?

Net metering up to 500 kW; gross metering up to 1 MW; group and virtual net metering below 100 kW. The rule is the same across Madhya Pradesh.

How much electricity does a solar plant generate in Bhopal?

About 1,370 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 13.7 lakh units a year. A site study gives the figure to plan on.

Where is Somaya Solar based, and how far is that from Bhopal?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 600 km from Bhopal in a straight line. The closest published project is KRIBHCO (2 MW rooftop plant) in Shahjahanpur, about 570 km away.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Bhopal

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image