Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Dewas, Madhya Pradesh. Most of our published work is megawatt-scale rooftop plants on working industrial sites.
Dewas: industrial areas
The Madhya Pradesh Industrial Development Corporation (MPIDC) land bank lists Industrial Park Dewas 2 & 3 among its industrial areas in Dewas district.
The Government of India's One District One Product (ODOP) list names Bamboo as the product of Dewas district.
Metering rules for business rooftops in Dewas
In Madhya Pradesh, MPERC's Grid Interactive Renewable Energy Systems regulations of 14 March 2024 let consumers of all categories, including commercial and industrial, install rooftop or on-site renewable plants under net metering up to 500 kW. Gross metering is allowed up to 1 MW. Group net metering and virtual net metering are allowed below 100 kW. The regulations were amended on 18 June 2026. There is no net billing option in these regulations.
The size limits, charges and other conditions for Madhya Pradesh are on the page Commercial & Industrial Solar in Madhya Pradesh.
In Dewas the application for connection and metering goes to MPPaKVVCL.
Output and bill value for a rooftop plant in Dewas
A solar plant in Dewas is modelled to produce about 1,380 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the HT Industrial (HV-3.1), 11 kV supply energy charge of ₹7.79 per kWh (MPERC retail supply tariff order for FY 2026-27, Petition No. 140/2025, passed 26 March 2026). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. The rate of ₹7.79 per unit applies to energy up to 50% load factor; energy above 50% load factor is ₹6.79. A monthly fixed charge of ₹409 per kVA of billing demand also applies at 11 kV. At 33 kV the energy charge is ₹7.75 and ₹6.70, with a fixed charge of ₹641 per kVA. At 132 kV it is ₹7.34 and ₹6.35, with ₹729 per kVA. At 220/400 kV it is ₹6.89 and ₹5.89, with ₹729 per kVA. Time-of-day rebate or surcharge applies as set in the general terms of the HT tariff. A rebate of ₹1 per unit applies to new HT connections and, as an alternative, to incremental consumption of existing consumers, on the conditions in the order. The rates exclude taxes and duties. The same tariff order covers all three DISCOMs.
| Plant size | Modelled output a year | Shadow-free roof needed (typical) | Value at ₹7.79 per kWh |
|---|---|---|---|
| 100 kW | 1.4 lakh units | 1,000 sq m | ₹10.8 lakh |
| 250 kW | 3.5 lakh units | 2,500 sq m | ₹26.9 lakh |
| 500 kW | 6.9 lakh units | 5,000 sq m | ₹53.8 lakh |
| 1 MW | 13.8 lakh units | 10,000 sq m | ₹1.08 crore |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
How a factory or commercial rooftop project runs
Rooftop plants on working buildings are planned around the roof, the load and the production schedule.
- Roof check: sheet or concrete, load capacity, shading and safe access
- Sizing against daytime load and sanctioned demand, within the metering rules above
- Mounting design to suit the roof, including corrosion protection where the air is harsh
- Installation in stages so production carries on
- Testing, metering and connection with the electricity supplier
- Monitoring and maintenance after handover, where contracted
More detail: Commercial & Industrial Solar across India.
Rooftop projects by Somaya Solar near Dewas
These are the Somaya Solar projects closest to Dewas, with straight-line distances. They are shown as references and are not in Dewas unless the line says so.
- KRIBHCO: 2 MW rooftop plant, Shahjahanpur, Uttar Pradesh, about 670 km from Dewas. Fertiliser plant; the structures carry a special coating against corrosion. Five years of operation and maintenance.
- Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 750 km from Dewas. Completed in two months, with five years of operation and maintenance.
- Akums Limited: 2.3 MW rooftop plant, SIDCUL, Haridwar, Uttarakhand, about 800 km from Dewas. In progress. The roof is more than 70 feet above the ground, so material is lifted by several cranes.
Questions about solar projects in Dewas
Which electricity company handles solar connections in Dewas?
Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited (MPPaKVVCL) supplies electricity in Dewas district, one of the districts it lists as its area.
Is net metering available for factories and commercial buildings in Dewas?
Net metering up to 500 kW; gross metering up to 1 MW; group and virtual net metering below 100 kW. The rule is the same across Madhya Pradesh.
How much electricity does a solar plant generate in Dewas?
About 1,380 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 13.8 lakh units a year. A site study gives the figure to plan on.
Where is Somaya Solar based, and how far is that from Dewas?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 650 km from Dewas in a straight line. The closest published project is KRIBHCO (2 MW rooftop plant) in Shahjahanpur, about 670 km away.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Dewas
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- DPIIT, ODOP Product List V32 (19 August 2025); copy hosted by the Embassy of India, Algiers
- Energy Department, Govt of Madhya Pradesh: MP West Discom page
- GeoNames (place coordinates, CC BY 4.0)
- Invest MP / MPIDC: Madhya Pradesh Industrial Park Profiles & Land Bank 2023 (contents list)
- MPERC (Grid Interactive Renewable Energy Systems and Related Matters) Regulations [Revision II], 2024 {RG-39(II) of 2024}, dated 14 March 2024, with the First Amendment of 18 June 2026
- MPERC ARR and Retail Supply Tariff Order for FY 2026-27, 26 March 2026 (tariff schedule HV-3)
- PVGIS, European Commission Joint Research Centre (solar output model)