Somaya Solar Solutions Limited delivers turnkey solar projects in Kamarhati, West Bengal: one contract that runs from the first survey to a commissioned plant with its approvals in place.
What turnkey means in practice
In a turnkey contract you hand over the site and the requirement and take back a working plant. One contract covers every step in between.
- One price and one schedule covering design, supply, installation and commissioning
- Approvals and metering paperwork handled by the contractor
- Defined tests before handover, with drawings, warranties and manuals
- A named point of contact through the project
- Operation and maintenance after handover, where contracted
More detail: Turnkey Solar EPC across India.
Steps in a turnkey project in Kamarhati
- Survey of the site and a study of twelve months of bills
- Design, drawings and a fixed-price proposal
- Application to the electricity supplier (CESC) for connection and metering
- Equipment supply and installation
- Testing, inspection and commissioning
- Handover with drawings, warranties and monitoring access
Approvals a turnkey contract covers in Kamarhati
In West Bengal, rooftop solar for every consumer category is governed by WBERC's Grid Interactive Rooftop Solar Photovoltaic System for Prosumers Regulations, 2025, notified on 31 July 2025. A consumer may choose net metering, net billing or gross metering. Net metering is allowed from 1 kW up to 500 kW, or up to the contract demand or sanctioned load, whichever is lower. Net billing and gross metering are allowed up to the contract demand or sanctioned load. WBERC lists no amendment to these regulations.
The size limits, charges and other conditions for West Bengal are on the page Turnkey Solar EPC in West Bengal.
In Kamarhati the application for connection and metering goes to CESC.
What to expect from the plant in Kamarhati
A solar plant in Kamarhati is modelled to produce about 1,270 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the Industries (11 kV), Rate E(B), high voltage energy charge of ₹7.07 per kWh (WBERC tariff order for WBSEDCL for 2025-26, dated 20 March 2025, in force from 1 April 2025 and continuing until further order). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. The rate is the summer rate; it is ₹7.06 per unit in monsoon and ₹7.05 in winter. At 33 kV the rates are ₹6.91, ₹6.89 and ₹6.87; at 132 kV ₹6.77, ₹6.75 and ₹6.73. A demand charge of ₹384 per kVA per month also applies. An optional time-of-day scheme at 11 kV charges ₹6.95 (6 AM to 5 PM), ₹8.37 (5 PM to 11 PM) and ₹5.18 (11 PM to 6 AM) in summer; at 220 kV only time-of-day rates apply. Electricity duty and taxes are extra. A green tariff of 50 paise per unit applies on top for consumers who ask for green power. Consumers in the former DPL area of Durgapur still pay DPL's tariff as on 31 December 2018. Other licensees have their own orders: CESC charges ₹6.81 per unit (summer) for HV industries below 33 kV and ₹6.58 at 33 kV (order of 25 March 2025), and DVC charges ₹6.21 at 11 kV (order of 31 March 2025), each with a demand charge of ₹384 per kVA per month. No WBERC tariff order for 2026-27 was listed on WBERC's website on 18 November 2026.
| Plant size | Modelled output a year | Shadow-free roof needed (typical) | Value at ₹7.07 per kWh |
|---|---|---|---|
| 100 kW | 1.3 lakh units | 1,000 sq m | ₹9.0 lakh |
| 500 kW | 6.3 lakh units | 5,000 sq m | ₹44.9 lakh |
| 1 MW | 12.7 lakh units | 10,000 sq m | ₹89.8 lakh |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
Reference projects near Kamarhati
These are the Somaya Solar projects closest to Kamarhati, with straight-line distances. They are shown as references and are not in Kamarhati unless the line says so.
- KUSUM-C, Ram Sati Devi: 2.4 MW ground-mounted plant under PM-KUSUM Component C, Katni, Madhya Pradesh, about 830 km from Kamarhati. Completed, including the transmission line work coordinated with the local distribution company.
- KRIBHCO: 2 MW rooftop plant, Shahjahanpur, Uttar Pradesh, about 1030 km from Kamarhati. Fertiliser plant; the structures carry a special coating against corrosion. Five years of operation and maintenance.
- Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 1190 km from Kamarhati. Completed in two months, with five years of operation and maintenance.
Questions about solar projects in Kamarhati
Which electricity company handles solar connections in Kamarhati?
CESC Limited (CESC) supplies Kamarhati, which the cited source places in its supply area.
Is net metering available for factories and commercial buildings in Kamarhati?
Net metering up to 500 kW; net billing and gross metering up to the contract demand. The rule is the same across West Bengal.
How much electricity does a solar plant generate in Kamarhati?
About 1,270 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 12.7 lakh units a year. A site study gives the figure to plan on.
Where is Somaya Solar based, and how far is that from Kamarhati?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 1280 km from Kamarhati in a straight line. The closest published project is KUSUM-C, Ram Sati Devi (2.4 MW ground-mounted plant under PM-KUSUM Component C) in Katni, about 830 km away.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Kamarhati
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- CESC: source naming Kamarhati within its supply area
- GeoNames (place coordinates, CC BY 4.0)
- PVGIS, European Commission Joint Research Centre (solar output model)
- WBERC (Grid Interactive Rooftop Solar Photovoltaic System for Prosumers) Regulations, 2025, Notification No. 81/WBERC, Kolkata Gazette of 31 July 2025; WBERC suo-motu order SM-40/25-26 of 20 August 2025 (feed-in tariff)
- WBERC tariff order for WBSEDCL for 2025-26, Case No. TP-98/22-23, dated 20 March 2025 (paragraph 3.3, Annexure 3B3); CESC tariff order for 2025-26 dated 25 March 2025 (Annexure 3A2); DVC tariff order for 2025-26 dated 31 March 2025 (Annexure 3A2)