Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Tumkur, Karnataka. Most of our published work is megawatt-scale rooftop plants on working industrial sites.

Local points for solar projects in Tumkur

The Government of India's One District One Product (ODOP) list names Machine Tool and Coir based Industries as the products of Tumakuru district.

Metering rules for business rooftops in Tumkur

In Karnataka, net metering is open to every consumer category, including commercial and industrial. The plant may be up to the sanctioned load or contract demand, or 1,000 kW, whichever is lower. The Distributed Solar PV (DSPV) Plants Regulations, 2026 set this. They were notified on 19 August 2026, published in the gazette on 24 August 2026, and replaced the 2016 rooftop regulations.

The size limits, charges and other conditions for Karnataka are on the page Commercial & Industrial Solar in Karnataka.

In Tumkur the application for connection and metering goes to BESCOM.

Output and bill value for a rooftop plant in Tumkur

A solar plant in Tumkur is modelled to produce about 1,400 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the HT-2(a) Industrial, rate the Tariff Order 2025 fixes for FY2026-27 energy charge of ₹6.60 per kWh (KERC Combined Tariff Order 2025 for the ESCOMs, dated 27 March 2025 (FY2025-26 to FY2027-28), and KERC review order of 3 March 2026). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. The Tariff Order 2025 fixes the HT-2(a) energy charge for FY2026-27 at 660 paise per kWh, with a demand charge of ₹350 per kVA per month. KERC's review order of 3 March 2026 re-fixed HT-2(a) for FY2025-26 at ₹6.70 per unit and ₹365 per kVA. It does not say what applies for FY2026-27; the table uses the ₹6.60 the Tariff Order 2025 fixes for that year. The same HT-2(a) schedule applies to all five distribution companies. A time-of-day tariff applies (plus 100 paise at 06:00-09:00 and 18:00-22:00 and minus 100 paise at 22:00-06:00, December to June). BESCOM consumers also pay an FY25 true-up charge per unit from May 2026 to April 2027. Confirm the rate with the distribution company.

Plant sizeModelled output a yearShadow-free roof needed (typical)Value at ₹6.60 per kWh
100 kW1.4 lakh units1,000 sq m₹9.2 lakh
250 kW3.5 lakh units2,500 sq m₹23.1 lakh
500 kW7.0 lakh units5,000 sq m₹46.2 lakh
1 MW14.0 lakh units10,000 sq m₹92.4 lakh

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

How a factory or commercial rooftop project runs

Rooftop plants on working buildings are planned around the roof, the load and the production schedule.

  • Roof check: sheet or concrete, load capacity, shading and safe access
  • Sizing against daytime load and sanctioned demand, within the metering rules above
  • Mounting design to suit the roof, including corrosion protection where the air is harsh
  • Installation in stages so production carries on
  • Testing, metering and connection with the electricity supplier
  • Monitoring and maintenance after handover, where contracted

More detail: Commercial & Industrial Solar across India.

Rooftop projects by Somaya Solar near Tumkur

These are the Somaya Solar projects closest to Tumkur, with straight-line distances. They are shown as references and are not in Tumkur unless the line says so.

  • KRIBHCO: 2 MW rooftop plant, Shahjahanpur, Uttar Pradesh, about 1640 km from Tumkur. Fertiliser plant; the structures carry a special coating against corrosion. Five years of operation and maintenance.
  • Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 1770 km from Tumkur. Completed in two months, with five years of operation and maintenance.
  • Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand, about 1850 km from Tumkur. Included net-metering coordination with the local electricity distribution company.

See all published projects

Questions about solar projects in Tumkur

Which electricity company handles solar connections in Tumkur?

Bangalore Electricity Supply Company Limited (BESCOM) supplies electricity in Tumakuru district, one of the districts it lists as its area.

Is net metering available for factories and commercial buildings in Tumkur?

Net metering up to the sanctioned load or 1,000 kW, whichever is lower. The rule is the same across Karnataka.

How much electricity does a solar plant generate in Tumkur?

About 1,400 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 14.0 lakh units a year. A site study gives the figure to plan on.

Where is Somaya Solar based, and how far is that from Tumkur?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 1700 km from Tumkur in a straight line. The closest published project is KRIBHCO (2 MW rooftop plant) in Shahjahanpur, about 1640 km away.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Tumkur

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image