Turnkey Solar EPC Solutions in Ajmer

Somaya Solar Solutions Limited delivers turnkey solar projects in Ajmer, Rajasthan: one contract that runs from the first survey to a commissioned plant with its approvals in place.

What turnkey means in practice

In a turnkey contract you hand over the site and the requirement and take back a working plant. One contract covers every step in between.

  • One price and one schedule covering design, supply, installation and commissioning
  • Approvals and metering paperwork handled by the contractor
  • Defined tests before handover, with drawings, warranties and manuals
  • A named point of contact through the project
  • Operation and maintenance after handover, where contracted

More detail: Turnkey Solar EPC across India.

Steps in a turnkey project in Ajmer

  1. Survey of the site and a study of twelve months of bills
  2. Design, drawings and a fixed-price proposal
  3. Application to the electricity supplier (TPADL / AVVNL) for connection and metering
  4. Equipment supply and installation
  5. Testing, inspection and commissioning
  6. Handover with drawings, warranties and monitoring access

Approvals a turnkey contract covers in Ajmer

In Rajasthan, net metering is open to every consumer category, including commercial and industrial, for loads up to 1 MW or up to the sanctioned load or contract demand, whichever is lower. The regulator set this limit in its order of 7 February 2024; before that it was 500 kW.

The size limits, charges and other conditions for Rajasthan are on the page Turnkey Solar EPC in Rajasthan.

Ajmer's supply is run by TPADL, so that is the company to ask first about connecting a rooftop plant in the city. The licence stays with AVVNL. Ask for the current steps before you apply, because the process for a commercial or industrial connection can change.

What to expect from the plant in Ajmer

A solar plant in Ajmer is modelled to produce about 1,460 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the Large Industrial (HT-5, 11 kV) energy charge of ₹6.50 per unit (RERC tariff order of 30 March 2026, in force from 1 April 2026). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise.

Plant sizeModelled output a yearShadow-free roof needed (typical)Value at ₹6.50 per unit
100 kW1.5 lakh units1,000 sq m₹9.5 lakh
500 kW7.3 lakh units5,000 sq m₹47.5 lakh
1 MW14.6 lakh units10,000 sq m₹94.9 lakh

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

Reference projects near Ajmer

These are the Somaya Solar projects closest to Ajmer, with straight-line distances. They are shown as references and are not in Ajmer unless the line says so.

  • KUSUM-A, Bhavnath Singh: 2.4 MW ground-mounted plant under PM-KUSUM Component A, Amroha, Uttar Pradesh, about 470 km from Ajmer. In progress. Site access was difficult and was handled with local support.
  • Akums Limited: 2.3 MW rooftop plant, SIDCUL, Haridwar, Uttarakhand, about 510 km from Ajmer. In progress. The roof is more than 70 feet above the ground, so material is lifted by several cranes.
  • Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand, about 520 km from Ajmer. Included net-metering coordination with the local electricity distribution company.

See all published projects

Questions about solar projects in Ajmer

Which electricity company handles solar connections in Ajmer?

TP Ajmer Distribution Limited (TPADL) has run electricity distribution in Ajmer city since 1 July 2017 as the distribution franchisee of Ajmer Vidyut Vitran Nigam Limited (AVVNL), which holds the licence.

Is net metering available for factories and commercial buildings in Ajmer?

Net metering up to 1 MW, within the sanctioned load. The rule is the same across Rajasthan.

How much electricity does a solar plant generate in Ajmer?

About 1,460 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 14.6 lakh units a year. A site study gives the figure to plan on.

Where is Somaya Solar based, and how far is that from Ajmer?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 370 km from Ajmer in a straight line. The closest published project is KUSUM-A, Bhavnath Singh (2.4 MW ground-mounted plant under PM-KUSUM Component A) in Amroha, about 470 km away.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Ajmer

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 17 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image