Turnkey Solar EPC Solutions in Dharamshala

Somaya Solar Solutions Limited delivers turnkey solar projects in Dharamshala, Himachal Pradesh: one contract that runs from the first survey to a commissioned plant with its approvals in place.

What turnkey means in practice

In a turnkey contract you hand over the site and the requirement and take back a working plant. One contract covers every step in between.

  • One price and one schedule covering design, supply, installation and commissioning
  • Approvals and metering paperwork handled by the contractor
  • Defined tests before handover, with drawings, warranties and manuals
  • A named point of contact through the project
  • Operation and maintenance after handover, where contracted

More detail: Turnkey Solar EPC across India.

Steps in a turnkey project in Dharamshala

  1. Survey of the site and a study of twelve months of bills
  2. Design, drawings and a fixed-price proposal
  3. Application to the electricity supplier (HPSEBL) for connection and metering
  4. Equipment supply and installation
  5. Testing, inspection and commissioning
  6. Handover with drawings, warranties and monitoring access

Approvals a turnkey contract covers in Dharamshala

In Himachal Pradesh a consumer of HPSEBL can install rooftop solar under net metering up to 50 kWp. A system above 50 kWp and up to 1 MWp goes under net billing. The rules are in HPERC's Rooftop Solar PV Grid Interactive System Regulations, 2015, as amended four times, most recently on 19 August 2026.

The size limits, charges and other conditions for Himachal Pradesh are on the page Turnkey Solar EPC in Himachal Pradesh.

In Dharamsala the application for connection and metering goes to HPSEBL.

What to expect from the plant in Dharamshala

A solar plant in Dharamshala is modelled to produce about 1,360 units (kWh) a year for each kW installed, for a rooftop array at a 10° tilt. The last column values that energy at the Large Industrial Power Supply (LIPS), HT-1, contract demand above 100 kVA and up to 1 MVA energy charge of ₹5.85 per kVAh (HPERC tariff order for HPSEBL for 2026-27, dated 25 March 2026, in force from 1 April 2026). It leaves out fixed and demand charges, surcharges, duty and the effect of the metering rules, so it is a rough guide, not a savings promise. The rate is ₹5.60 per kVAh for HT-2 (contract demand above 1 MVA), ₹5.55 at 66 kV, ₹5.50 at 132 kV and ₹5.45 at 220 kV and above. A demand charge also applies each month: ₹250 per kVA for HT-1, ₹400 per kVA for HT-2 and ₹425 per kVA for EHT. It is charged on the recorded maximum demand or 85% of the contract demand, whichever is higher. Energy used in peak hours (6:30 PM to 10 PM) is charged at ₹6.95 per kVAh for HT and ₹6.75 for EHT. The rates exclude electricity duty and taxes. HPSEBL is the only licensee, so the schedule applies across the state.

Plant sizeModelled output a yearShadow-free roof needed (typical)Value at ₹5.85 per kVAh
100 kW1.4 lakh units1,000 sq m₹8.0 lakh
500 kW6.8 lakh units5,000 sq m₹39.8 lakh
1 MW13.6 lakh units10,000 sq m₹79.6 lakh

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

Reference projects near Dharamshala

These are the Somaya Solar projects closest to Dharamshala, with straight-line distances. They are shown as references and are not in Dharamshala unless the line says so.

  • Akums Limited: 2.3 MW rooftop plant, SIDCUL, Haridwar, Uttarakhand, about 300 km from Dharamshala. In progress. The roof is more than 70 feet above the ground, so material is lifted by several cranes.
  • Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand, about 310 km from Dharamshala. Included net-metering coordination with the local electricity distribution company.
  • Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand, about 420 km from Dharamshala. Completed in two months, with five years of operation and maintenance.

See all published projects

Questions about solar projects in Dharamshala

Which electricity company handles solar connections in Dharamshala?

Himachal Pradesh State Electricity Board Limited (HPSEBL) is the distribution utility for Himachal Pradesh and supplies Kangra district.

Is net metering available for factories and commercial buildings in Dharamshala?

Net metering up to 50 kWp; net billing above 50 kWp up to 1 MWp. The rule is the same across Himachal Pradesh.

How much electricity does a solar plant generate in Dharamshala?

About 1,360 units (kWh) a year for each kW installed, by the PVGIS model with cautious loss settings. A 1 MW plant works out to about 13.6 lakh units a year. A site study gives the figure to plan on.

Where is Somaya Solar based, and how far is that from Dharamshala?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh, about 410 km from Dharamshala in a straight line. The closest published project is Akums Limited (2.3 MW rooftop plant) in SIDCUL, Haridwar, about 300 km away.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Dharamshala

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image