Somaya Solar Solutions Limited is a solar EPC company that takes up rooftop and ground-mounted projects in Meghalaya. EPC means one contractor does the engineering, buys the equipment, builds the plant and hands it over working.
Meghalaya at a glance for solar projects
| Electricity regulator | Meghalaya State Electricity Regulatory Commission (MSERC) |
|---|---|
| State renewable energy agency | Meghalaya New and Renewable Energy Development Agency (MNREDA) |
| Electricity distribution | MePDCL (The whole state of Meghalaya) |
| State solar policy | Meghalaya Power Policy, 2024 (in force until 31 March 2030 unless notified otherwise) |
| Rooftop metering for businesses | Commercial and industrial: net billing up to the sanctioned load or 500 kW, whichever is lower; gross metering up to 10 MW |
What our EPC scope covers
An EPC contract puts engineering, procurement and construction with one company, so one party answers for design, equipment and the working plant.
- Site survey and a study of your electricity use and bills
- Plant design, drawings and equipment selection
- Supply of modules, inverters, mounting structures and electrical equipment
- Installation, testing and commissioning
- Paperwork and coordination with the electricity supplier for connection and metering, where it is in the contract
- Operation and maintenance after handover, where contracted
More detail: Solar EPC Company across India.
Connecting a plant to the grid in Meghalaya
In Meghalaya, net metering is open only to domestic, agricultural, group housing, charitable, government and local authority consumers. A commercial or industrial consumer can use net billing, gross metering or behind-the-meter. The rules are in MSERC's Grid Interactive Distributed Renewable Energy Sources (2 of 2026) Regulations, 2026, notified on 30 April 2026. They replaced the 2015 rooftop net metering regulations.
- Net metering is for domestic, agricultural, group housing, charitable institution, government building and local authority consumers only.
- Net billing is open to all categories, from 1 kW up to the sanctioned load or contract demand or 500 kW, whichever is lower. Exports are credited at 100% of the weighted average tariff of solar projects of 5 MW or above found through competitive bidding in the last financial year, or a reference rate set by MSERC. Imports are billed at the retail tariff. Any net credit at the end of the settlement period is paid to the consumer.
- Gross metering is open to all categories, up to 10 MW, in the consumer's premises or at another location. All the energy generated is sold to the distribution company.
- Behind-the-meter is open to all categories, from 1 kW up to the sanctioned load or contract demand.
- Group and virtual net metering are open only to the same categories as net metering.
- No grid support charge applies to net metering, net billing or gross metering. MSERC may set one for group net metering, virtual net metering and behind-the-meter systems.
- The total of rooftop and other distributed plants on a distribution transformer may not exceed 80% of its rated capacity, or 100% of a feeder's capacity.
- An application up to the sanctioned load or 10 kW, whichever is lower, is deemed accepted without a feasibility study.
- On 1 October 2026 MSERC pre-published a draft First Amendment and invited comments until 14 October 2026. It is a draft. Whether it has been notified is not confirmed.
What a plant produces in Meghalaya
Solar output changes across Meghalaya with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,150 to 1,200 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Jowai | 1,190 | 1,260 |
| Khliehriat | 1,200 | 1,260 |
| Nongstoin | 1,150 | 1,210 |
| Resubelpara | 1,160 | 1,220 |
| Shillong | 1,170 | 1,240 |
| Tura | 1,190 | 1,260 |
| Williamnagar | 1,150 | 1,220 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
Questions about solar projects in Meghalaya
Is net metering available for factories and commercial buildings in Meghalaya?
In Meghalaya, net metering is open only to domestic, agricultural, group housing, charitable, government and local authority consumers. A commercial or industrial consumer can use net billing, gross metering or behind-the-meter. The rules are in MSERC's Grid Interactive Distributed Renewable Energy Sources (2 of 2026) Regulations, 2026, notified on 30 April 2026. They replaced the 2015 rooftop net metering regulations.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Meghalaya
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- MSERC (Grid Interactive Distributed Renewable Energy Sources) (2 of 2026) Regulations, 2026, notification of 30 April 2026; MSERC public notice of 1 October 2026
- MSERC order in Case No. 11 of 2025 (MePDCL distribution tariff for FY 2026-27), dated 26 March 2026
- Meghalaya New And Renewable Energy Development Agency (State Nodal Agency for MNRE); MSERC DRE Regulations, 2026 preamble
- Meghalaya Power Policy 2024 (Power Department, Government of Meghalaya), chapter VII and clauses 1 and 3
- Meghalaya State Electricity Regulatory Commission
- PVGIS, European Commission Joint Research Centre (solar output model)