Commercial and Industrial Rooftop Solar in Bihar

Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Bihar. Most of our published work is megawatt-scale rooftop plants on working industrial sites.

Metering rules for business rooftops in Bihar

In Bihar, any eligible consumer of NBPDCL or SBPDCL, including commercial and industrial consumers, can install rooftop solar under net metering or gross metering. The system must be at least 1 kWp and may not exceed the consumer's sanctioned or contracted load. The rules are in BERC's Rooftop Solar Grid Interactive Systems Based on Net and Gross Metering Regulations, 2018, as amended on 24 July 2024. On 8 October 2026 BERC published a draft Second Amendment for comment. It was not final when we checked.

  • A consumer on net metering cannot also take gross metering. Neither arrangement allows banking.
  • Under net metering the settlement period runs from 1 April to 31 March. Surplus energy left at the end of that period is neither paid for nor carried forward. Under gross metering the licensee pays the Feed-in Tariff approved by BERC for the year.
  • Net metering is capped at 100 MW a year in each licensee's area. The total rooftop capacity on one distribution transformer may not exceed 80% of the transformer's capacity.
  • The 2024 amendment says the licensee must finish the technical feasibility study within 15 days, or the proposal is treated as feasible. Applications up to 10 kW are deemed accepted without a study.
  • The draft Second Amendment would cap net metering at 500 kWp or the sanctioned load, whichever is lower, allow gross metering up to the sanctioned load, and pay year-end surplus at 50% of the Feed-in Tariff. Comments were due by 28 October 2026 and the hearing was on 3 November 2026. Ask the licensee whether it has been notified.
  • The state policy refers to virtual and group net metering but says only that they may be promoted with suitable regulations. The 2018 regulations do not mention them.

Output and bill value for a rooftop plant in Bihar

Solar output changes across Bihar with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,220 to 1,370 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Amarpur1,3101,370
Araria1,2501,330
Areraj1,3401,420
Arrah1,3701,430
Arwal1,3701,440
Aurangabad1,3701,430
Bagaha1,3301,400
Bahadurganj1,2201,300
Bairagnia1,3301,410
Bakhri1,3201,390
Bakhtiyarpur1,3601,420
Banka1,3201,380
Banmankhi Bazar1,2801,350
Barauli1,3501,420
Barauni1,3501,420
Barbigha1,3601,430
Barh1,3601,420
Barhiya1,3301,400
Begusarai1,3401,410
Belsand1,3401,410
Benipur1,3201,390
Bettiah1,3401,420
Bhabhua1,3701,430
Bhagalpur1,3101,380
Bihar Sharif1,3601,430
Bihariganj1,3001,360
Bihat1,3401,410
Bihta1,3601,430
Bikram1,3701,440
Bikramganj1,3701,440
Bodh Gaya1,3601,430
Buxar1,3701,440
Chakia1,3401,410
Chanpatia1,3401,420
Chapra1,3601,430
Colgong1,2901,360
Dalsingh Sarai1,3401,410
Darbhanga1,3301,400
Daudnagar1,3701,440
Dhaka1,3401,420
Dighwara1,3601,430
Dinapur Cantonment1,3601,430
Dinapur Nizamat1,3601,430
Dumraon1,3701,440
Fatwa1,3501,420
Forbesganj1,2501,330
Gaya1,3601,430
Gogri Jamalpur1,3201,380
Gopalganj1,3501,430
Hajipur1,3601,430
Hilsa1,3601,430
Hisua1,3601,420
Islampur1,3701,430
Jagdispur1,3701,440
Jahanabad1,3701,440
Jainagar1,2901,370
Jamalpur1,3301,390
Jamui1,3501,410
Jhajha1,3401,410
Jhanjharpur1,3001,370
Jogbani1,2501,330
Kasba1,2601,330
Kataiya1,3601,430
Katihar1,2601,330
Khagaria1,3201,390
Khagaul1,3601,420
Kharagpur1,3201,380
Kishanganj1,2401,310
Koelwar1,3601,430
Lalganj1,3501,420
Luckeesarai1,3501,410
Madhepura1,2901,360
Madhubani1,3101,380
Maharajgani1,3601,430
Mahnar Bazar1,3501,420
Mairwa1,3701,440
Makhdumpur1,3701,430
Maner1,3701,430
Manihari1,2701,340
Marhaura1,3601,430
Masaurhi Buzurg1,3601,430
Mehsi1,3401,410
Mokameh1,3501,410
Mothihari1,3401,420
Motipur1,3401,410
Munger1,3301,390
Murliganj1,2901,360
Muzaffarpur1,3401,410
Nabinagar1,3701,430
Narkatiaganj1,3201,400
Nasriganj1,3701,440
Naubatpur1,3701,440
Naugachhia1,2901,360
Nawada1,3601,420
Nirmali1,2801,350
Nokha1,3701,440
Pakridayal1,3401,420
Patna1,3601,420
Phulwari Sharif1,3601,420
Piro1,3701,440
Purnia1,2701,340
Rafiganj1,3701,430
Rajauli1,3601,430
Rajgir1,3701,430
Ramnagar1,3201,400
Raxaul1,3401,420
Revelganj1,3601,430
Rosera1,3201,390
Saharsa1,3001,370
Sahibganj1,3401,420
Samastipur1,3301,400
Sasaram1,3701,440
Sheikhpura1,3501,410
Sheohar1,3401,410
Sherghati1,3701,430
Silao1,3701,430
Sitamarhi1,3401,410
Siwan1,3601,440
Sonepur1,3601,430
Sultanganj1,3201,390
Supaul1,3001,370
Teghra1,3501,420
Tekari1,3701,440
Waris Aliganj1,3601,420

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

How a factory or commercial rooftop project runs

Rooftop plants on working buildings are planned around the roof, the load and the production schedule.

  • Roof check: sheet or concrete, load capacity, shading and safe access
  • Sizing against daytime load and sanctioned demand, within the metering rules above
  • Mounting design to suit the roof, including corrosion protection where the air is harsh
  • Installation in stages so production carries on
  • Testing, metering and connection with the electricity supplier
  • Monitoring and maintenance after handover, where contracted

More detail: Commercial & Industrial Solar across India.

Questions about solar projects in Bihar

Is net metering available for factories and commercial buildings in Bihar?

In Bihar, any eligible consumer of NBPDCL or SBPDCL, including commercial and industrial consumers, can install rooftop solar under net metering or gross metering. The system must be at least 1 kWp and may not exceed the consumer's sanctioned or contracted load. The rules are in BERC's Rooftop Solar Grid Interactive Systems Based on Net and Gross Metering Regulations, 2018, as amended on 24 July 2024. On 8 October 2026 BERC published a draft Second Amendment for comment. It was not final when we checked.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Bihar

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.