Commercial and Industrial Rooftop Solar in Jharkhand

Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Jharkhand. Most of our published work is megawatt-scale rooftop plants on working industrial sites.

Metering rules for business rooftops in Jharkhand

In Jharkhand, rooftop solar for any consumer of a distribution licensee, including commercial and industrial consumers, goes through JSERC's Rooftop Solar PV Grid Interactive System and Net/Gross Metering Regulations, 2015. The regulations have been amended seven times. The latest, the Seventh Amendment, was notified on 30 January 2026 and changed only the fees.

  • A rooftop plant may be from 1 kWp to 2 MWp, and not more than 100% of the consumer's sanctioned load or contract demand.
  • The consumer chooses either net metering or gross metering for a premises, not both.
  • The capacity allowed on one distribution transformer is 100% of its rated capacity, or another percentage the Commission fixes. An application may not be rejected only because the network needs strengthening.
  • Since the Fifth Amendment of 26 November 2024, the voltage at which the plant connects follows clause 4.3 of the JSERC Electricity Supply Code Regulations, 2015.
  • Under net metering, surplus power carries forward as a credit within the financial year. Where the tariff is billed in kVAh, import and export are measured in kVAh. At the end of the year, unadjusted credit is paid at the rate JSERC notifies.
  • The JBVNL tariff order for 2026-27 keeps the surplus power rate for net metering at ₹3.80 per unit and for gross metering at ₹4.16 per unit. The order says these are the rates set for 2023-24, which stay effective until a later order.
  • Group net metering and virtual net metering are allowed under separate JSERC regulations of 9 May 2024, and apply to all eligible consumers who have no arrears. The regulations exempt such systems from wheeling, banking and cross-subsidy charges, as decided by the Commission case by case.
  • Since the Fourth Amendment of 29 May 2024, an application for up to 10 kW that is complete is deemed accepted without a technical feasibility study.
  • Under the Sixth Amendment, applicants under PM Surya Ghar through the national portal pay no application or registration fee. The Seventh Amendment sets the application fee at ₹250 up to 50 kW, ₹750 above 50 kW up to 1 MWp and ₹1,500 above 1 MWp up to 2 MWp. The registration fee is ₹1,000, ₹2,500 and ₹5,000 for the same sizes.

Output and bill value for a rooftop plant in Jharkhand

Solar output changes across Jharkhand with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,270 to 1,370 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Barki Saria1,3501,410
Bishrampur1,3701,430
Bokaro1,3401,390
Bundu1,3301,380
Chaibasa1,3201,370
Chakradharpur1,3201,370
Chandrapura1,3401,390
Chas1,3401,390
Chatra1,3601,420
Chirkunda1,3201,380
Chitarpur1,3401,400
Churi1,3601,420
Deoghar1,3301,390
Dhanbad1,3301,380
Dugda1,3401,390
Dumka1,3101,370
Garhwa1,3601,420
Ghatsila1,3101,360
Giridih1,3401,400
Godda1,3101,370
Gomoh1,3301,390
Gumia1,3401,390
Gumla1,3501,400
Hazaribagh1,3601,420
Husainabad1,3701,430
Jamshedpur1,3201,370
Jamtara1,3201,380
Jaridih1,3301,390
Jhumri Telaiya1,3601,430
Kathhara1,3401,390
Khalari1,3601,420
Khunti1,3401,390
Kodarma1,3601,430
Kuju1,3401,400
Latehar1,3401,400
Lohardaga1,3501,410
Madhupur1,3301,390
Medininagar1,3601,420
Mushabani1,3101,360
Pakur1,2801,350
Patratu1,3501,410
Phusro1,3301,390
Rajmahal1,2701,330
Ranchi1,3501,400
Ratu1,3601,420
Sahibganj1,2801,350
Saunda1,3501,410
Simdega1,3301,390
Siuliban1,3201,380

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

How a factory or commercial rooftop project runs

Rooftop plants on working buildings are planned around the roof, the load and the production schedule.

  • Roof check: sheet or concrete, load capacity, shading and safe access
  • Sizing against daytime load and sanctioned demand, within the metering rules above
  • Mounting design to suit the roof, including corrosion protection where the air is harsh
  • Installation in stages so production carries on
  • Testing, metering and connection with the electricity supplier
  • Monitoring and maintenance after handover, where contracted

More detail: Commercial & Industrial Solar across India.

Questions about solar projects in Jharkhand

Is net metering available for factories and commercial buildings in Jharkhand?

In Jharkhand, rooftop solar for any consumer of a distribution licensee, including commercial and industrial consumers, goes through JSERC's Rooftop Solar PV Grid Interactive System and Net/Gross Metering Regulations, 2015. The regulations have been amended seven times. The latest, the Seventh Amendment, was notified on 30 January 2026 and changed only the fees.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Jharkhand

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.