Somaya Solar Solutions Limited takes up megawatt-scale, grid-connected solar plants in Jharkhand as an EPC contractor: engineering, supply, construction and commissioning.
What Jharkhand's policy says about large solar plants
The Jharkhand State Solar Policy 2022 is the state's current solar policy. The Department of Energy issued it by resolution dated 5 July 2022. It stays valid for five years from notification unless another policy replaces it.
- Target: 4,000 MW of solar by 2027, made up of 720 MW distributed solar (including 250 MW rooftop and 220 MW captive), 280 MW off-grid and 3,000 MW utility scale.
- The Jharkhand Renewable Energy Development Agency (JREDA) is the state nodal agency.
- The policy encourages captive and group-captive solar plants, with a minimum capacity of 100 kW. A plant may be at the consumer's premises or elsewhere under virtual and group net metering.
- Captive solar projects through open access are exempted from the cross-subsidy surcharge and the additional surcharge. Transmission and distribution losses still apply.
- Banking of 100% of energy is permitted in all 12 months, with prior approval of the Transco or distribution company. Banking is adjusted in kind at 5% of the energy delivered, and banking charges are exempted for grid-connected rooftop solar.
Under JSERC's Green Energy Open Access Regulations, 2024, a consumer with a contract demand or sanctioned load of 100 kW or more can take renewable power through open access. A captive consumer has no load limit.
- There is no capacity limit on a captive renewable plant in relation to the consumer's contract demand or sanctioned load.
- Banking is allowed monthly. The banking charge is 8% of the energy banked, and unused banked energy lapses at the end of each monthly banking cycle.
- The cross-subsidy surcharge and the additional surcharge do not apply to energy from a captive plant used by its owner. They are also exempt for solar projects under 25 MW that sell to third parties within the state.
- For 2026-27 the JBVNL tariff order sets a cross-subsidy surcharge of ₹1.95 per unit for HT consumers at 11 kV and at 33 kV and above.
- The same order lists wheeling charges of ₹0.65 per unit at 11 kV and ₹0.25 per unit at 33 kV and above. It says an open access consumer pays no charge for the use of the distribution network other than wheeling charge and the cross-subsidy surcharge.
Output and land at megawatt scale in Jharkhand
Solar output changes across Jharkhand with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,330 to 1,430 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Barki Saria | 1,350 | 1,410 |
| Bishrampur | 1,370 | 1,430 |
| Bokaro | 1,340 | 1,390 |
| Bundu | 1,330 | 1,380 |
| Chaibasa | 1,320 | 1,370 |
| Chakradharpur | 1,320 | 1,370 |
| Chandrapura | 1,340 | 1,390 |
| Chas | 1,340 | 1,390 |
| Chatra | 1,360 | 1,420 |
| Chirkunda | 1,320 | 1,380 |
| Chitarpur | 1,340 | 1,400 |
| Churi | 1,360 | 1,420 |
| Deoghar | 1,330 | 1,390 |
| Dhanbad | 1,330 | 1,380 |
| Dugda | 1,340 | 1,390 |
| Dumka | 1,310 | 1,370 |
| Garhwa | 1,360 | 1,420 |
| Ghatsila | 1,310 | 1,360 |
| Giridih | 1,340 | 1,400 |
| Godda | 1,310 | 1,370 |
| Gomoh | 1,330 | 1,390 |
| Gumia | 1,340 | 1,390 |
| Gumla | 1,350 | 1,400 |
| Hazaribagh | 1,360 | 1,420 |
| Husainabad | 1,370 | 1,430 |
| Jamshedpur | 1,320 | 1,370 |
| Jamtara | 1,320 | 1,380 |
| Jaridih | 1,330 | 1,390 |
| Jhumri Telaiya | 1,360 | 1,430 |
| Kathhara | 1,340 | 1,390 |
| Khalari | 1,360 | 1,420 |
| Khunti | 1,340 | 1,390 |
| Kodarma | 1,360 | 1,430 |
| Kuju | 1,340 | 1,400 |
| Latehar | 1,340 | 1,400 |
| Lohardaga | 1,350 | 1,410 |
| Madhupur | 1,330 | 1,390 |
| Medininagar | 1,360 | 1,420 |
| Mushabani | 1,310 | 1,360 |
| Pakur | 1,280 | 1,350 |
| Patratu | 1,350 | 1,410 |
| Phusro | 1,330 | 1,390 |
| Rajmahal | 1,270 | 1,330 |
| Ranchi | 1,350 | 1,400 |
| Ratu | 1,360 | 1,420 |
| Sahibganj | 1,280 | 1,350 |
| Saunda | 1,350 | 1,410 |
| Simdega | 1,330 | 1,390 |
| Siuliban | 1,320 | 1,380 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
What utility-scale work involves
At megawatt scale the grid connection, land and delivery schedule decide the project as much as the equipment does.
- Land and grid-connection feasibility
- Detailed engineering for the plant and the evacuation system
- Procurement and logistics for modules, inverters, transformers and structures
- Civil, mechanical and electrical construction with several teams working in parallel
- Testing, commissioning and connection with the transmission or distribution utility
- Operation and maintenance, where contracted
More detail: Utility-Scale Solar across India.
Questions about solar projects in Jharkhand
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Jharkhand
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- JSERC (Terms and Conditions for Green Energy Open-access) Regulations, 2024, notified 9 May 2024; JSERC order for JBVNL dated 25 March 2026 (chapter 10)
- Jharkhand State Solar Policy 2022 (Department of Energy, Government of Jharkhand, Resolution dated 5 July 2022)
- PVGIS, European Commission Joint Research Centre (solar output model)