Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Mizoram. Most of our published work is megawatt-scale rooftop plants on working industrial sites.

Metering rules for business rooftops in Mizoram

In Mizoram, rooftop solar falls under the JERC for Manipur and Mizoram (Metering for Grid Connected Renewable Energy) Regulations, 2016, as amended in 2016, 2022 and twice in 2023. MZERC adopted them on 26 July 2024, from 23 July 2024, and the 2026 MZERC orders still apply them.

  • Net metering is limited to 10 kW. There is no capacity limit under gross metering. A rooftop system must be at least 1 kWp and at most 1 MWp (AC side) for one consumer, and one above 500 kWp is considered only if the distribution system stays stable.
  • The total solar capacity connected to a feeder or distribution transformer may not exceed 100% of its capacity. The licensee's total yearly intake is also limited to the target set for its renewable purchase obligation.
  • Surplus credits left at the end of the settlement period, which is the financial year, are paid at the average power purchase cost fixed by the Commission. For 2026-27 MZERC fixed it at ₹4.67 per kWh by its order of 11 May 2026.
  • The monthly fixed charge is levied on the contract demand or contracted load, not on the solar capacity.
  • After site inspection the licensee must tell the consumer the outcome of the feasibility check within 3 days, and sign the connection agreement within 20 days of approval (Fourth Amendment, 15 December 2023).
  • The title of the Second Amendment (19 October 2022) says 'draft', but MZERC's adoption order lists it as the Second Amendment Regulation, 2022, so it is treated as in force.

Output and bill value for a rooftop plant in Mizoram

Solar output changes across Mizoram with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,260 to 1,300 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Aizawl1,2801,340
Hnahthial1,2901,340
Khawzawl1,3001,350
Kolasib1,2601,320
Lawngtlai1,3001,350
Lunglei1,2801,330
Saiha1,2901,340
Saitual1,2901,340
Serchhip1,2901,350

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

How a factory or commercial rooftop project runs

Rooftop plants on working buildings are planned around the roof, the load and the production schedule.

  • Roof check: sheet or concrete, load capacity, shading and safe access
  • Sizing against daytime load and sanctioned demand, within the metering rules above
  • Mounting design to suit the roof, including corrosion protection where the air is harsh
  • Installation in stages so production carries on
  • Testing, metering and connection with the electricity supplier
  • Monitoring and maintenance after handover, where contracted

More detail: Commercial & Industrial Solar across India.

Questions about solar projects in Mizoram

Is net metering available for factories and commercial buildings in Mizoram?

In Mizoram, rooftop solar falls under the JERC for Manipur and Mizoram (Metering for Grid Connected Renewable Energy) Regulations, 2016, as amended in 2016, 2022 and twice in 2023. MZERC adopted them on 26 July 2024, from 23 July 2024, and the 2026 MZERC orders still apply them.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Mizoram

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image