Somaya Solar Solutions Limited takes up megawatt-scale, grid-connected solar plants in Mizoram as an EPC contractor: engineering, supply, construction and commissioning.

What Mizoram's policy says about large solar plants

The Solar Power Policy of Mizoram, 2025 is the state's current solar policy. The Governor notified it on 25 February 2025 and it stays in force until a new policy replaces it or a further order is made. The State Government decided to review the earlier Solar Power Policy of 2017.

  • Target: 275 MW of solar by 2029-30, of which 270 MW is grid-scale solar parks, 4.5 MW rooftop and 0.5 MW solar pumps.
  • The Power & Electricity Department is the State Nodal Agency, and ZEDA is the implementing agency for rooftop solar.
  • Captive projects are a recognised category. They must follow section 9 of the Electricity Act, 2003 and the rules and orders of the Commission.
  • Electricity duty is exempted for captive consumption, sale to the distribution licensee and third-party sale from solar projects set up in the state.
  • Banking of energy is allowed for up to one year, with banking charges of 2% in kind. Unredeemed banked energy is treated as bought by the Department at the average pooled power purchase cost set by the Commission.
  • Open access and transmission charges follow the Commission's and CERC's regulations. The Commission's green energy open access regulations set the banking charge at 8%, which is not the same as the 2% in the policy.

Under the JERC Open Access Regulations, 2010 that MZERC adopted, open access is allowed for consumers with a connected load of 1 MW and above. The JERC green energy open access charges regulations, also adopted by MZERC, cover consumers with a contracted demand or sanctioned load of 100 kW or more, except captive users.

  • Banked green energy carries a banking charge of 8% of the energy banked, adjusted in kind. The state's Solar Power Policy of 2025 says 2% for banking, so the two official documents differ.
  • The cross-subsidy surcharge for green energy open access may not exceed 20% of the tariff or average billing rate of the consumer category.
  • Wheeling charge for 2026-27: ₹1.239 per kWh, set by the tariff order of 25 March 2026. P&ED had asked for ₹1.67.
  • No cross-subsidy surcharge or additional surcharge figure for 2026-27 was found in the tariff order.

Output and land at megawatt scale in Mizoram

Solar output changes across Mizoram with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,320 to 1,350 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Aizawl1,2801,340
Hnahthial1,2901,340
Khawzawl1,3001,350
Kolasib1,2601,320
Lawngtlai1,3001,350
Lunglei1,2801,330
Saiha1,2901,340
Saitual1,2901,340
Serchhip1,2901,350

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

What utility-scale work involves

At megawatt scale the grid connection, land and delivery schedule decide the project as much as the equipment does.

  • Land and grid-connection feasibility
  • Detailed engineering for the plant and the evacuation system
  • Procurement and logistics for modules, inverters, transformers and structures
  • Civil, mechanical and electrical construction with several teams working in parallel
  • Testing, commissioning and connection with the transmission or distribution utility
  • Operation and maintenance, where contracted

More detail: Utility-Scale Solar across India.

Questions about solar projects in Mizoram

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Mizoram

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image