Somaya Solar Solutions Limited builds ground-mounted solar power plants in Himachal Pradesh for businesses that want their own power and for landowners and developers who sell power to the grid.
Output and land for a ground-mounted plant in Himachal Pradesh
Solar output changes across Himachal Pradesh with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,440 to 1,480 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Baddi | 1,370 | 1,480 |
| Chamba | 1,370 | 1,460 |
| Dharamshala | 1,360 | 1,470 |
| Mandi | 1,330 | 1,440 |
| Nahan | 1,360 | 1,460 |
| Paonta Sahib | 1,360 | 1,460 |
| Shimla | 1,350 | 1,440 |
| Solan | 1,370 | 1,470 |
| Sundarnagar | 1,340 | 1,450 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
State policy and open access in Himachal Pradesh
The Swaran Jayanti Energy Policy, 2021 is the state's energy policy. The Government of Himachal Pradesh notified it on 20 January 2022 and has amended it since. The regulator applied it in orders of 22 July 2026 and 9 October 2026.
- HPSEBL must buy the power from solar projects of up to 5 MW if the project is commissioned on or before 31 March 2030. The price is the HPERC tariff in force on the date the project is allotted.
- HIMURJA gives the in-principle approval for solar projects of 250 kW to 5 MW under its scheme for allotment and registration of solar power projects.
- An HPERC order of 22 March 2025 records that, under paragraph 4.3.5 of the policy, solar projects of 250 kW to 1 MW are allotted to bonafide Himachalis only.
- The state charges a royalty of 5 paise per unit on solar projects above 1 MW, under an amendment to the policy dated 21 September 2023.
- For solar projects above 5 MW the nodal agency is the Directorate of Energy, Government of Himachal Pradesh. Its scheme, published in March 2026, takes applications all year for projects on the developer's own or leased private land, including projects for captive use by industries.
- Under that scheme the developer may sell the power anywhere or use it for captive use. The state charges a royalty of 5 paise per unit, and the application fee is ₹20,000 per MW.
- Developers who are not Himachalis can start work only after approval under section 118 of the HP Tenancy and Land Reforms Act.
HPERC's tariff order for 2026-27 says open access is permitted for all consumers with a contracted demand or connected load above 100 kW. The order sets the open access charges that apply from 1 April 2026.
- Cross-subsidy surcharge for large industrial consumers on long-term and medium-term open access in 2026-27: ₹0.66 per unit at EHT, ₹0.55 per unit for HT-1 (above 100 kVA and up to 1 MVA) and ₹0.59 per unit for HT-2 (above 1 MVA).
- For short-term open access the same rates apply in non-peak hours. In peak hours the surcharge is ₹0.70 per unit at EHT, ₹0.58 for HT-1 and ₹0.62 for HT-2.
- The additional surcharge is 63.66 paise per unit from 1 April 2026.
- Wheeling charges for short-term open access in 2026-27: 175 paise per unit at 11 kV to below 33 kV, 79 paise at 33 kV, 30 paise at 66 kV, 22 paise at 132 kV and 6 paise at 220 kV.
- Long-term and medium-term open access users pay wheeling charges per MW per month: ₹7,60,572 at 11 kV to below 33 kV, ₹3,39,013 at 33 kV, ₹1,26,868 at 66 kV, ₹91,687 at 132 kV and ₹25,609 at 220 kV.
- Open access consumers bear distribution losses in kind: 2.5% at 220 kV or 132 kV, 4% at 66 kV, 6% at 33 kV and 8% at 22 kV or 11 kV.
- The cross-subsidy surcharge and additional surcharge do not apply to energy bought through open access for a period in which HPSEBL told the consumer in advance that it could not supply that part of the demand.
- The concessional wheeling charge for renewable generators of up to 25 MW in the state is not available for supply to open access consumers or to captive consumers.
- HPERC made the Terms and Conditions for Green Energy Open Access and Banking Regulations, 2024 on 17 December 2024 and lists them among its current regulations. The regulations say they come into force on a date the Commission notifies.
What a ground-mounted project involves
A ground-mounted plant needs more groundwork than a rooftop one before any module is fixed.
- Land check: title, slope, soil, drainage, access road and shading
- Distance to the substation or connection point and the line needed to reach it
- Layout, structure design and foundations for the soil
- Supply, installation, testing and commissioning
- Evacuation line, metering and connection approvals
- Fencing, cleaning water and maintenance planning
More detail: Ground-Mounted Solar Plant across India.
Questions about solar projects in Himachal Pradesh
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Himachal Pradesh
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 17 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- HPERC orders of 22 July 2026 (Petition No. 121 of 2026), 9 October 2026 (Petition No. 179 of 2026) and 22 March 2025 (Petition No. 20 of 2025), which apply the Swaran Jayanti Energy Policy, 2021; Directorate of Energy, Government of Himachal Pradesh, scheme for solar power projects above 5 MW (published 10 March 2026)
- HPERC tariff order for HPSEBL for 2026-27, dated 25 March 2026 (chapter 10, Open Access); HPERC (Terms and Conditions for Green Energy Open Access and Banking) Regulations, 2024, notification of 17 December 2024
- PVGIS, European Commission Joint Research Centre (solar output model)