Somaya Solar Solutions Limited builds ground-mounted solar power plants in Tamil Nadu for businesses that want their own power and for landowners and developers who sell power to the grid.
Output and land for a ground-mounted plant in Tamil Nadu
Solar output changes across Tamil Nadu with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,330 to 1,500 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Ambattur | 1,360 | 1,360 |
| Avadi | 1,360 | 1,360 |
| Chennai | 1,390 | 1,390 |
| Coimbatore | 1,360 | 1,360 |
| Dindigul | 1,340 | 1,350 |
| Erode | 1,370 | 1,370 |
| Hosur | 1,410 | 1,410 |
| Kallakurichi | 1,330 | 1,340 |
| Kanchipuram | 1,350 | 1,350 |
| Karur | 1,390 | 1,390 |
| Madurai | 1,330 | 1,340 |
| Nagercoil | 1,500 | 1,500 |
| Ooty | 1,390 | 1,400 |
| Ranipet | 1,340 | 1,340 |
| Salem | 1,370 | 1,380 |
| Sivakasi | 1,370 | 1,370 |
| Thanjavur | 1,330 | 1,330 |
| Thoothukudi | 1,470 | 1,470 |
| Tiruchirappalli | 1,350 | 1,360 |
| Tirunelveli | 1,410 | 1,410 |
| Tiruppur | 1,390 | 1,390 |
| Vellore | 1,340 | 1,350 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
State policy and open access in Tamil Nadu
Under TNERC's Green Energy Open Access Regulations, 2025 (notified 18 September 2025), any EHT or HT consumer with a contracted demand of 63 kVA or more can take renewable power through open access.
- Banking is allowed within the consumer's calendar-month billing cycle. The banking charge is 8% of the energy banked, taken in kind. Banked credit does not carry over to the next billing cycle.
- Banked energy left unused at the end of the banking period is bought by the distribution company at 75% of the applicable RE tariff for normal RE captive users.
- Charges include transmission, wheeling, cross-subsidy surcharge, additional surcharge, banking, standby, reactive energy and scheduling charges. Apart from banking, they follow TNERC's orders. A consumer who buys green energy through another state or a power exchange does not get the concessional charges for the state network.
- For FY 2025-26 the tariff order sets a wheeling (network) charge of ₹1.04 per kWh for HT and a cross-subsidy surcharge of ₹1.99 per kWh for HT-IA industry. The order stays in force until TNERC issues the next order.
- A person who qualifies as a captive generating plant keeps the right to open access under section 9 of the Electricity Act.
What a ground-mounted project involves
A ground-mounted plant needs more groundwork than a rooftop one before any module is fixed.
- Land check: title, slope, soil, drainage, access road and shading
- Distance to the substation or connection point and the line needed to reach it
- Layout, structure design and foundations for the soil
- Supply, installation, testing and commissioning
- Evacuation line, metering and connection approvals
- Fencing, cleaning water and maintenance planning
More detail: Ground-Mounted Solar Plant across India.
Questions about solar projects in Tamil Nadu
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Tamil Nadu
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.