PM-KUSUM Solar Plant EPC in Tamil Nadu

Somaya Solar Solutions Limited is an EPC contractor for PM-KUSUM solar plants. This page sets out how the scheme works for land and pumps in Tamil Nadu and what we do on such a project.

What PM-KUSUM covers

PM-KUSUM is a central government scheme of the Ministry of New and Renewable Energy, run in each state by state implementing agencies. Capacity is allotted to states on demand. The Ministry told the Lok Sabha on 29 July 2026 that the scheme's timeline is extended to 31 March 2027 for all components.

  • Component A: decentralised solar plants of up to 2 MW on farmers' land.
  • Component B: solar pumps for agriculture.
  • Component C: solarisation of grid-connected agriculture pumps, including feeder-level solarisation.

Who runs PM-KUSUM in Tamil Nadu

In Tamil Nadu the Agricultural Engineering Department runs Component B (standalone solar pumps). For Component A, the MNRE portal names TANGEDCO (now TNPDCL) as the State Implementing Agency, and TNGECL floated a tender for the 420 MW that TNERC approved. The Ministry of New and Renewable Energy reports nothing under Component C.

  • Progress reported to the Lok Sabha up to 30 June 2026: 3 MW under Component A (1 MW in 2024-25 and 2 MW in 2025-26), 5,186 solar pumps installed under Component B between 2020-21 and 2025-26, and nothing under Component C.
  • In an order of 29 December 2023, TNERC set a ceiling tariff of ₹3.30 per unit for 25 years for the 420 MW of Component A power and adopted ₹3.28 per unit for 3 MW. On 13 February 2025 TNERC dismissed a TNGECL petition for 5 MW more at ₹3.28 per unit and told it to issue a revised tender. Check the tariff in force with TNPDCL or TNGECL before signing.
  • The central government has extended the scheme to 31 March 2027 for all components.

What a PM-KUSUM plant produces in Tamil Nadu

Solar output changes across Tamil Nadu with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,330 to 1,500 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Ambattur1,3601,360
Avadi1,3601,360
Chennai1,3901,390
Coimbatore1,3601,360
Dindigul1,3401,350
Erode1,3701,370
Hosur1,4101,410
Kallakurichi1,3301,340
Kanchipuram1,3501,350
Karur1,3901,390
Madurai1,3301,340
Nagercoil1,5001,500
Ooty1,3901,400
Ranipet1,3401,340
Salem1,3701,380
Sivakasi1,3701,370
Thanjavur1,3301,330
Thoothukudi1,4701,470
Tiruchirappalli1,3501,360
Tirunelveli1,4101,410
Tiruppur1,3901,390
Vellore1,3401,350

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

What Somaya Solar does on a PM-KUSUM plant

Somaya Solar works as the EPC contractor for the farmer, developer or group that holds the allocation. It does not allot capacity or decide subsidy.

  • Site check of the land and its distance from the substation
  • Plant design and equipment supply
  • Installation, testing and commissioning
  • The line to the substation and coordination with the electricity supplier
  • Support with the documents the implementing agency asks for

More detail: PM-KUSUM across India.

Questions about solar projects in Tamil Nadu

Who do I apply to for PM-KUSUM in Tamil Nadu?

In Tamil Nadu the Agricultural Engineering Department runs Component B (standalone solar pumps). For Component A, the MNRE portal names TANGEDCO (now TNPDCL) as the State Implementing Agency, and TNGECL floated a tender for the 420 MW that TNERC approved. The Ministry of New and Renewable Energy reports nothing under Component C.

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Tamil Nadu

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.