Utility-Scale Solar Power Plant Installation in Tamil Nadu

Somaya Solar Solutions Limited takes up megawatt-scale, grid-connected solar plants in Tamil Nadu as an EPC contractor: engineering, supply, construction and commissioning.

What Tamil Nadu's policy says about large solar plants

Under TNERC's Green Energy Open Access Regulations, 2025 (notified 18 September 2025), any EHT or HT consumer with a contracted demand of 63 kVA or more can take renewable power through open access.

  • Banking is allowed within the consumer's calendar-month billing cycle. The banking charge is 8% of the energy banked, taken in kind. Banked credit does not carry over to the next billing cycle.
  • Banked energy left unused at the end of the banking period is bought by the distribution company at 75% of the applicable RE tariff for normal RE captive users.
  • Charges include transmission, wheeling, cross-subsidy surcharge, additional surcharge, banking, standby, reactive energy and scheduling charges. Apart from banking, they follow TNERC's orders. A consumer who buys green energy through another state or a power exchange does not get the concessional charges for the state network.
  • For FY 2025-26 the tariff order sets a wheeling (network) charge of ₹1.04 per kWh for HT and a cross-subsidy surcharge of ₹1.99 per kWh for HT-IA industry. The order stays in force until TNERC issues the next order.
  • A person who qualifies as a captive generating plant keeps the right to open access under section 9 of the Electricity Act.

Output and land at megawatt scale in Tamil Nadu

Solar output changes across Tamil Nadu with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,330 to 1,500 units per kW.

PlaceRooftop, 10° tilt (kWh per kW a year)Ground-mounted, best fixed tilt (kWh per kW a year)
Ambattur1,3601,360
Avadi1,3601,360
Chennai1,3901,390
Coimbatore1,3601,360
Dindigul1,3401,350
Erode1,3701,370
Hosur1,4101,410
Kallakurichi1,3301,340
Kanchipuram1,3501,350
Karur1,3901,390
Madurai1,3301,340
Nagercoil1,5001,500
Ooty1,3901,400
Ranipet1,3401,340
Salem1,3701,380
Sivakasi1,3701,370
Thanjavur1,3301,330
Thoothukudi1,4701,470
Tiruchirappalli1,3501,360
Tirunelveli1,4101,410
Tiruppur1,3901,390
Vellore1,3401,350

Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.

What utility-scale work involves

At megawatt scale the grid connection, land and delivery schedule decide the project as much as the equipment does.

  • Land and grid-connection feasibility
  • Detailed engineering for the plant and the evacuation system
  • Procurement and logistics for modules, inverters, transformers and structures
  • Civil, mechanical and electrical construction with several teams working in parallel
  • Testing, commissioning and connection with the transmission or distribution utility
  • Operation and maintenance, where contracted

More detail: Utility-Scale Solar across India.

Questions about solar projects in Tamil Nadu

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Tamil Nadu

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image