Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Assam. Most of our published work is megawatt-scale rooftop plants on working industrial sites.
Metering rules for business rooftops in Assam
In Assam, rooftop solar is governed by the AERC (Grid Interactive Solar PV Systems) Regulations, 2019, notified on 6 August 2019 and amended on 18 June 2024. APDCL has asked the regulator to cut net metering benefits and stop paying for surplus energy. AERC has not changed the rules. On 5 August 2026 it told APDCL to keep processing applications under the existing rules while the petition is pending.
- A system may be from 1 kWp to 1,000 kWp. For an HT consumer it is limited to 100% of the connected load or contract demand, where the grid connection is technically feasible.
- The total rooftop capacity on one distribution transformer may not exceed 80% of the transformer's capacity.
- Excess energy in a billing period is carried forward as credit. At the end of the settlement period, APDCL pays for unadjusted surplus at the average power purchase cost (APPC) approved by AERC, and the carried-over balance is reset to zero.
- APDCL's Petition No. 09/2026 asks that net metering be limited to residential consumers up to 10 kWp and that unadjusted surplus at year end not be paid for. AERC found the financial analysis incomplete and, pending a decision, told APDCL not to defer or reject applications because of the petition.
- The State Solar Policy 2025, clause 10.1 (as quoted in the order), says net metering is for residential consumers up to 10 kW and net billing for all categories, including residential above 10 kW. It adds that the arrangement follows AERC regulations and orders. Confirm with APDCL which arrangement applies to a commercial or industrial application.
- Deemed acceptance and automatic load enhancement apply to rooftop systems up to 10 kW under the central rules, and AERC directed APDCL to operationalise them.
- The state clean energy policy says rooftop projects can go under net metering, net billing, virtual net metering or group net metering as per the AERC regulations.
Output and bill value for a rooftop plant in Assam
Solar output changes across Assam with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,100 to 1,260 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Barpeta | 1,180 | 1,240 |
| Barpeta Road | 1,140 | 1,200 |
| Bilasipara | 1,170 | 1,240 |
| Biswanath Chariali | 1,150 | 1,220 |
| Bongaigaon | 1,160 | 1,230 |
| Chapar | 1,150 | 1,220 |
| Dergaon | 1,150 | 1,210 |
| Dhekiajuli | 1,130 | 1,200 |
| Dhing | 1,160 | 1,230 |
| Dhubri | 1,170 | 1,250 |
| Dibrugarh | 1,150 | 1,220 |
| Digboi | 1,120 | 1,190 |
| Diphu | 1,210 | 1,270 |
| Dum Duma | 1,130 | 1,200 |
| Garamur | 1,150 | 1,220 |
| Gauripur | 1,180 | 1,250 |
| Goalpara | 1,160 | 1,230 |
| Golaghat | 1,150 | 1,210 |
| Guwahati | 1,170 | 1,240 |
| Haflong | 1,260 | 1,320 |
| Hailakandi | 1,230 | 1,290 |
| Hamren | 1,180 | 1,230 |
| Hojai | 1,190 | 1,250 |
| Jorhat | 1,150 | 1,210 |
| Kokrajhar | 1,150 | 1,220 |
| Lanka | 1,200 | 1,250 |
| Mangaldai | 1,160 | 1,230 |
| Margherita | 1,130 | 1,200 |
| Mariani | 1,150 | 1,210 |
| Morigaon | 1,170 | 1,230 |
| Mushalpur | 1,170 | 1,240 |
| Nagaon | 1,170 | 1,240 |
| Nalbari | 1,180 | 1,260 |
| North Lakhimpur | 1,140 | 1,210 |
| Rangia | 1,180 | 1,250 |
| Sibsagar | 1,150 | 1,210 |
| Silapathar | 1,100 | 1,170 |
| Silchar | 1,230 | 1,290 |
| Sonari | 1,150 | 1,220 |
| Tezpur | 1,160 | 1,230 |
| Tinsukia | 1,140 | 1,210 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
How a factory or commercial rooftop project runs
Rooftop plants on working buildings are planned around the roof, the load and the production schedule.
- Roof check: sheet or concrete, load capacity, shading and safe access
- Sizing against daytime load and sanctioned demand, within the metering rules above
- Mounting design to suit the roof, including corrosion protection where the air is harsh
- Installation in stages so production carries on
- Testing, metering and connection with the electricity supplier
- Monitoring and maintenance after handover, where contracted
More detail: Commercial & Industrial Solar across India.
Questions about solar projects in Assam
Is net metering available for factories and commercial buildings in Assam?
In Assam, rooftop solar is governed by the AERC (Grid Interactive Solar PV Systems) Regulations, 2019, notified on 6 August 2019 and amended on 18 June 2024. APDCL has asked the regulator to cut net metering benefits and stop paying for surplus energy. AERC has not changed the rules. On 5 August 2026 it told APDCL to keep processing applications under the existing rules while the petition is pending.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Assam
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- AERC order sheet of 5 August 2026, Petition No. 09/2026, which reproduces the AERC (Grid Interactive Solar PV Systems) Regulations, 2019 and the First Amendment of 18 June 2024; Assam Integrated Clean Energy Policy, 2025, clause 6.1
- PVGIS, European Commission Joint Research Centre (solar output model)