Somaya Solar Solutions Limited builds ground-mounted solar power plants in Assam for businesses that want their own power and for landowners and developers who sell power to the grid.
Output and land for a ground-mounted plant in Assam
Solar output changes across Assam with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,170 to 1,320 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Barpeta | 1,180 | 1,240 |
| Barpeta Road | 1,140 | 1,200 |
| Bilasipara | 1,170 | 1,240 |
| Biswanath Chariali | 1,150 | 1,220 |
| Bongaigaon | 1,160 | 1,230 |
| Chapar | 1,150 | 1,220 |
| Dergaon | 1,150 | 1,210 |
| Dhekiajuli | 1,130 | 1,200 |
| Dhing | 1,160 | 1,230 |
| Dhubri | 1,170 | 1,250 |
| Dibrugarh | 1,150 | 1,220 |
| Digboi | 1,120 | 1,190 |
| Diphu | 1,210 | 1,270 |
| Dum Duma | 1,130 | 1,200 |
| Garamur | 1,150 | 1,220 |
| Gauripur | 1,180 | 1,250 |
| Goalpara | 1,160 | 1,230 |
| Golaghat | 1,150 | 1,210 |
| Guwahati | 1,170 | 1,240 |
| Haflong | 1,260 | 1,320 |
| Hailakandi | 1,230 | 1,290 |
| Hamren | 1,180 | 1,230 |
| Hojai | 1,190 | 1,250 |
| Jorhat | 1,150 | 1,210 |
| Kokrajhar | 1,150 | 1,220 |
| Lanka | 1,200 | 1,250 |
| Mangaldai | 1,160 | 1,230 |
| Margherita | 1,130 | 1,200 |
| Mariani | 1,150 | 1,210 |
| Morigaon | 1,170 | 1,230 |
| Mushalpur | 1,170 | 1,240 |
| Nagaon | 1,170 | 1,240 |
| Nalbari | 1,180 | 1,260 |
| North Lakhimpur | 1,140 | 1,210 |
| Rangia | 1,180 | 1,250 |
| Sibsagar | 1,150 | 1,210 |
| Silapathar | 1,100 | 1,170 |
| Silchar | 1,230 | 1,290 |
| Sonari | 1,150 | 1,220 |
| Tezpur | 1,160 | 1,230 |
| Tinsukia | 1,140 | 1,210 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
State policy and open access in Assam
The Government of Assam notified the Assam Integrated Clean Energy Policy, 2025 on 24 February 2025. It covers solar, wind and other clean energy projects. It stays in force until 31 March 2030 or until another policy replaces it. The regulator's order of 5 August 2026 also refers to a separate Assam Solar Generation Promotion Policy, 2025, notified on 5 June 2025.
- Target: 11,700 MW of renewable power projects up to 2029-30, including 1,000 MW of rooftop solar at industrial and commercial sites.
- APDCL, or another agency the state notifies, is the nodal agency under the policy.
- A captive solar plant for use within the state is limited to the consumer's contract demand. A consumer's plant may sell surplus power to APDCL at 75% of the APPC rate.
- Cross-subsidy surcharge and additional surcharge do not apply to power from clean energy projects that meet the captive generating plant criteria.
- Electricity duty is fully exempt on power consumed from renewable plants during the policy period, from the date of commissioning.
Open access in Assam is governed by the AERC (Terms and Conditions for Open Access) Regulations, 2024, published in the Assam Gazette on 4 December 2024. The tariff schedule for 2026-27 sets the open access charges below. The notice does not list an additional surcharge or a banking charge.
- A draft first amendment dated 24 September 2025 would allow green energy open access to consumers with a contracted demand or sanctioned load of 100 kW and above, also through several connections added together in one electricity division. It says there is no limit on load for captive use of green energy.
- Cross-subsidy surcharge for 2026-27: ₹1.81 per kWh for HT Industries-I and HT Industries-II, and ₹1.32 per kWh for HT Small Industries.
- Wheeling charge at 33 kV is ₹0.27 per kWh. Wheeling losses are 5% at 33 kV and 11% at 11 kV.
- Standby charge for HT Industries-II (above 150 kVA) is ₹2.49 per kWh.
- The state clean energy policy says cross-subsidy surcharge and additional surcharge do not apply to power from a plant that meets the captive generating plant criteria.
What a ground-mounted project involves
A ground-mounted plant needs more groundwork than a rooftop one before any module is fixed.
- Land check: title, slope, soil, drainage, access road and shading
- Distance to the substation or connection point and the line needed to reach it
- Layout, structure design and foundations for the soil
- Supply, installation, testing and commissioning
- Evacuation line, metering and connection approvals
- Fencing, cleaning water and maintenance planning
More detail: Ground-Mounted Solar Plant across India.
Questions about solar projects in Assam
How much land does a solar plant need?
A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Assam
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- APDCL notice of tariff schedule w.e.f. 1 April 2026 (AERC order of 6 March 2026); AERC draft notification of 24 September 2025 (Open Access Regulations, 2024, First Amendment); Assam Integrated Clean Energy Policy, 2025, clause 5.8
- Assam Integrated Clean Energy Policy, 2025 (Power Department, Government of Assam, notification PEL.19/2025/13, 24 February 2025); AERC order of 5 August 2026 (Petition No. 09/2026)
- PVGIS, European Commission Joint Research Centre (solar output model)