Somaya Solar Solutions Limited is a solar EPC company based in Ghaziabad, Uttar Pradesh. We design, supply, install and commission solar plants for factories, commercial buildings, institutions, landowners and PM-KUSUM developers in Uttarakhand.
Uttarakhand at a glance for solar projects
| Electricity regulator | Uttarakhand Electricity Regulatory Commission (UERC) |
|---|---|
| State renewable energy agency | Uttarakhand Renewable Energy Development Agency (UREDA) |
| Electricity distribution | UPCL (The whole state: all 13 districts, including Dehradun, Haridwar, Udham Singh Nagar, Nainital, Pauri, Tehri, Almora and Pithoragarh) |
| State solar policy | Uttarakhand State Solar Policy, 2023 (in force until another policy replaces it; targets run to December 2027) |
| Rooftop metering for businesses | Net metering up to 1 MW, within the sanctioned load |
Solar services in Uttarakhand
- Solar EPC Company in Uttarakhand
Design, supply, installation and commissioning of rooftop and ground-mounted plants under one contract. - Commercial & Industrial Solar in Uttarakhand
Rooftop solar for factories, warehouses, institutions and commercial buildings. - Ground-Mounted Solar Plant in Uttarakhand
Solar plants on open land for captive use or sale of power. - Utility-Scale Solar in Uttarakhand
Megawatt-scale plants that feed the grid or supply large consumers. - PM-KUSUM in Uttarakhand
EPC for farmer-owned and feeder-level solar plants under the PM-KUSUM scheme. - Turnkey Solar EPC in Uttarakhand
One contract from survey to a working plant, with approvals and handover included.
Solar output by place in Uttarakhand
Solar output changes across Uttarakhand with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,280 to 1,390 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Almora | 1,340 | 1,430 |
| Bazpur | 1,380 | 1,480 |
| Clement Town | 1,340 | 1,440 |
| Dehradun | 1,340 | 1,450 |
| Haldwani | 1,370 | 1,460 |
| Haridwar | 1,370 | 1,470 |
| Jaspur | 1,370 | 1,460 |
| Kashipur | 1,390 | 1,480 |
| Kichha | 1,380 | 1,470 |
| Kotdwara | 1,340 | 1,440 |
| Manglaur | 1,380 | 1,480 |
| Mussoorie | 1,330 | 1,420 |
| Naini Tal | 1,360 | 1,460 |
| Pauri | 1,290 | 1,400 |
| Pithoragarh | 1,280 | 1,370 |
| Ramnagar | 1,360 | 1,460 |
| Rishikesh | 1,330 | 1,420 |
| Roorkee | 1,380 | 1,480 |
| Rudrapur | 1,390 | 1,480 |
| Sitarganj | 1,370 | 1,470 |
| Srinagar | 1,300 | 1,400 |
| Tehri | 1,320 | 1,430 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
Somaya Solar projects in Uttarakhand
Somaya Solar's published projects in Uttarakhand:
- Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand. Completed in two months, with five years of operation and maintenance.
- Akums Limited: 2.3 MW rooftop plant, SIDCUL, Haridwar, Uttarakhand. In progress. The roof is more than 70 feet above the ground, so material is lifted by several cranes.
- Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand. Included net-metering coordination with the local electricity distribution company.
Places we cover in Uttarakhand
- Almora
- Bazpur
- Clement Town
- Dehradun
- Haldwani
- Haridwar
- Jaspur
- Kashipur
- Kichha
- Kotdwara
- Manglaur
- Mussoorie
- Naini Tal
- Pauri
- Pithoragarh
- Ramnagar
- Rishikesh
- Roorkee
- Rudrapur
- Sitarganj
- Srinagar
- Tehri
Questions about solar projects in Uttarakhand
Is net metering available for factories and commercial buildings in Uttarakhand?
In Uttarakhand, a commercial or industrial consumer of UPCL can install rooftop or small solar under net metering up to 100% of the sanctioned load or contract demand, with a ceiling of 1 MW. The rule is in Regulation 37 of the regulator's renewable energy regulations of 2023, as rewritten by the first amendment of 20 June 2024.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh. Its published projects in Uttarakhand are: Naini Papers Limited (3 MW rooftop plant, Kashipur); Akums Limited (2.3 MW rooftop plant, SIDCUL, Haridwar); Luminous (1 MW rooftop plant, Haridwar).
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Uttarakhand
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 17 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- PVGIS, European Commission Joint Research Centre (solar output model)
- UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2023, with the First Amendment of 20 June 2024 and the Second Amendment of 27 November 2025, and UERC generic tariff order of 4 June 2026
- UERC tariff order for UPCL for 2026-27, dated 30 March 2026 (section 6.1: UPCL is the sole distribution licensee)
- Uttarakhand Electricity Regulatory Commission
- Uttarakhand State Solar Policy, 2023 (Government of Uttarakhand, published by UREDA)
- Uttarakhand State Solar Policy, 2023 (Government of Uttarakhand, published by UREDA), and UERC order of 13 October 2026 in Misc. Application No. 08 of 2026