Somaya Solar Solutions Limited installs rooftop solar plants for factories, warehouses, institutions and commercial buildings in Uttarakhand. Most of our published work is megawatt-scale rooftop plants on working industrial sites.
Metering rules for business rooftops in Uttarakhand
In Uttarakhand, a commercial or industrial consumer of UPCL can install rooftop or small solar under net metering up to 100% of the sanctioned load or contract demand, with a ceiling of 1 MW. The rule is in Regulation 37 of the regulator's renewable energy regulations of 2023, as rewritten by the first amendment of 20 June 2024.
- Energy is settled on a net basis at the end of each billing period, which is one month.
- If the consumer exports more than it draws in a billing period, UPCL pays for the surplus at the regulator's generic tariff or the rate found through bidding, whichever is lower. The generic tariff is ₹2.00 per kWh for plants commissioned in 2026-27.
- The total rooftop capacity connected to one transformer may not exceed the capacity of that transformer.
- Group net metering lets one consumer set off surplus energy against its other connections in UPCL's area. A plant under group or virtual net metering must be between 5 kW and 75 kW. Virtual net metering is only for domestic consumers and offices of government and local authorities.
- The latest amendment is the second amendment, notified on 27 November 2025. It deals with battery energy storage and left the rooftop limits unchanged. In its reasons the regulator declined a request to remove the 1 MW ceiling.
- A consumer who needs more than 1 MW can set up a captive plant. The regulator has said a captive plant has no capacity restriction.
Output and bill value for a rooftop plant in Uttarakhand
Solar output changes across Uttarakhand with latitude, haze and temperature. The table shows modelled yearly output for each kW installed, for a low-tilt rooftop array and for a ground-mounted array at the best fixed tilt. Across these places the figure runs from about 1,280 to 1,390 units per kW.
| Place | Rooftop, 10° tilt (kWh per kW a year) | Ground-mounted, best fixed tilt (kWh per kW a year) |
|---|---|---|
| Almora | 1,340 | 1,430 |
| Bazpur | 1,380 | 1,480 |
| Clement Town | 1,340 | 1,440 |
| Dehradun | 1,340 | 1,450 |
| Haldwani | 1,370 | 1,460 |
| Haridwar | 1,370 | 1,470 |
| Jaspur | 1,370 | 1,460 |
| Kashipur | 1,390 | 1,480 |
| Kichha | 1,380 | 1,470 |
| Kotdwara | 1,340 | 1,440 |
| Manglaur | 1,380 | 1,480 |
| Mussoorie | 1,330 | 1,420 |
| Naini Tal | 1,360 | 1,460 |
| Pauri | 1,290 | 1,400 |
| Pithoragarh | 1,280 | 1,370 |
| Ramnagar | 1,360 | 1,460 |
| Rishikesh | 1,330 | 1,420 |
| Roorkee | 1,380 | 1,480 |
| Rudrapur | 1,390 | 1,480 |
| Sitarganj | 1,370 | 1,470 |
| Srinagar | 1,300 | 1,400 |
| Tehri | 1,320 | 1,430 |
Output figures are modelled with the European Commission's PVGIS tool (ERA5 weather data, 2005 to 2023) with system losses set at 20%, which is on the cautious side. Real output depends on shading, dust, equipment and layout. A site study gives the figure to plan on.
How a factory or commercial rooftop project runs
Rooftop plants on working buildings are planned around the roof, the load and the production schedule.
- Roof check: sheet or concrete, load capacity, shading and safe access
- Sizing against daytime load and sanctioned demand, within the metering rules above
- Mounting design to suit the roof, including corrosion protection where the air is harsh
- Installation in stages so production carries on
- Testing, metering and connection with the electricity supplier
- Monitoring and maintenance after handover, where contracted
More detail: Commercial & Industrial Solar across India.
Rooftop projects by Somaya Solar in Uttarakhand
Somaya Solar's published projects in Uttarakhand:
- Naini Papers Limited: 3 MW rooftop plant, Kashipur, Uttarakhand. Completed in two months, with five years of operation and maintenance.
- Akums Limited: 2.3 MW rooftop plant, SIDCUL, Haridwar, Uttarakhand. In progress. The roof is more than 70 feet above the ground, so material is lifted by several cranes.
- Luminous: 1 MW rooftop plant, Haridwar, Uttarakhand. Included net-metering coordination with the local electricity distribution company.
Questions about solar projects in Uttarakhand
Is net metering available for factories and commercial buildings in Uttarakhand?
In Uttarakhand, a commercial or industrial consumer of UPCL can install rooftop or small solar under net metering up to 100% of the sanctioned load or contract demand, with a ceiling of 1 MW. The rule is in Regulation 37 of the regulator's renewable energy regulations of 2023, as rewritten by the first amendment of 20 June 2024.
Where is Somaya Solar based?
Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh. Its published projects in Uttarakhand are: Naini Papers Limited (3 MW rooftop plant, Kashipur); Akums Limited (2.3 MW rooftop plant, SIDCUL, Haridwar); Luminous (1 MW rooftop plant, Haridwar).
What does Somaya Solar need to prepare a proposal?
Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.
Discuss a solar project in Uttarakhand
Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.
Email: info@somayasolar.com
Phone: +91-8700035846
Sources
Local rules and figures on this page were last checked on 17 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.
- PVGIS, European Commission Joint Research Centre (solar output model)
- UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) Regulations, 2023, with the First Amendment of 20 June 2024 and the Second Amendment of 27 November 2025, and UERC generic tariff order of 4 June 2026